Project Completion Certificate (Ground Water)
Scheme ID: 20097910 Name of Scheme: SONHI No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 3090 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 20-Sep-2024 Actual Date of Completion (Capex): 19-Jul-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Deep Tube well 25 Mtr / 126.10 Mtr Sonhi 25.861499 80.796975
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump (15 HP) 620 LPM / 60 Mtr Sonhi 25.861499 80.796975
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Elevated Storage Tank 200 KL / 14 Mtr Sonhi 25.861411 80.79689
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 Pipe 125 0.02150
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6 63 2.75975
2 HDPE Pipe PN-6 75 1.44620
3 HDPE Pipe PN-6 90 1.43220
4 HDPE Pipe PN-6 110 0.95290
5 HDPE Pipe PN-6 140 1.705
6 HDPE Pipe PN-6 160 0.3888
7 HDPE Pipe PN-6 200 0.658
HSC Connection
Sno. Total Nos.
1 586
Other Details
2.99
0.00
2.99
18-Jul-2025
19-Jul-2025