Project Completion Certificate (Ground Water)
Scheme ID: 20097920 Name of Scheme: TRILOCHANPUR No. of Villages: 2 No. of Habitation Covered: 4
Total Population Covered: 2940 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 14-May-2024 Actual Date of Completion (Capex): 30-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 22/79.90 TRILOCHANPIIR 25' .785449" N 80.920091"8
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 submersible 550/60 TRILOCHANPIIR 25' .785449" N 80.920091"8
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT.1 175/16 TRILOCHANPIIR 25' .785449" N 80.920091"8
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.t. K-9 100 0.02090
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 180 1.549
2 HDPE 160 0.462
3 HDPE 140 2.285
4 HDPE 125 0.339
5 HDPE 110 1.006
6 HDPE 90 1.169
7 HDPE 75 1.633
8 HDPE 63 3.856
HSC Connection
Sno. Total Nos.
1 549
Other Details
2.72
0.00
2.30
24-Apr-2025
25-Apr-2025