| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20098033 | Name of Scheme: Lakshmanpur Water Supply System | No. of Villages: 3 | No. of Habitation Covered: 4 |
| Total Population Covered: 3400 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 21-Apr-2024 | Actual Date of Completion (Capex): 29-Apr-2026 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 24/81.71 | Lakshmanpur | 26.6129 | 83.5808 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 42/43 | Lakshmanpur | 26.6129 | 83.5808 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Overhead Tank-1 | 200/16 | Lakshmanpur | 26.6129 | 83.5808 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.018 | Laying Completed |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 13.166 | Laying Completed |
| 2 | HDPE | 90 | 0.762 | Laying Completed |
| 3 | HDPE | 110 | 1.779 | Laying Completed |
| 4 | HDPE | 140 | 0.709 | Laying Completed |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |