| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20100230 | Name of Scheme: BIRDO NANGLI WSS | No. of Villages: 2 | No. of Habitation Covered: 2 |
| Total Population Covered: 2888 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 06-Jul-2023 | Actual Date of Completion (Capex): 04-Mar-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBE WELL | 30/144.43 | BIRDO NANGLI | 29.49550 | 78.29111 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 600/60 | BIRDO NANGLI | 29.49550 | 78.29111 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 175/16 | BIRDO NANGLI | 29.49550 | 78.29111 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI - K7 | 100 | 0.022 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 2.5026 | |
| 2 | HDPE | 75 | 1.3265 | |
| 3 | HDPE | 90 | 1.758 | |
| 4 | HDPE | 110 | 0.4274 | |
| 5 | HDPE | 125 | 0.1103 | |
| 6 | HDPE | 140 | 0.3702 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 391 |