Project Completion Certificate (Ground Water)
Scheme ID: 20100328 Name of Scheme: Sikri WSS No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1317 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 12-Mar-2025 Actual Date of Completion (Capex): 05-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 18 M / 112 M Sikri 28.382025 77.941247
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 250 LPM / 48 M Sikri 28.382025 77.941247
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 75 KL / 12 M Sikri 28.382161 77.941141
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. 100 0.0406
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 2.369
2 HDPE 75 0.178
3 HDPE 90 0.064
4 HDEP 110 1.69
HSC Connection
Sno. Total Nos.
1 295
Other Details
1.31
1.30
1.31
25-Jul-2025
26-Jul-2025