Project Completion Certificate (Ground Water)
Scheme ID: 2758991 Name of Scheme: Gajyee Kol No. of Villages: 1 No. of Habitation Covered: 2
Total Population Covered: 2390 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 12-Apr-2025 Actual Date of Completion (Capex): 10-Jul-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 36.15/101.69 Ganjaikol 26.5246 83.5021
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 30/41 Ganjaikol 26.5246 83.5021
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 (Retrofitting Work) - Ganjaikol 26.5246 83.5021
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.015 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8.452 Laying Completed
2 HDPE 90 0.091 Laying Completed
3 HDPE 140 0.741 Laying Completed
HSC Connection
Sno. Total Nos.
1 428
Other Details
1.41
0.00
1.41
09-Jul-2025
01-Feb-2026