| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 8359440 | Name of Scheme: Kheriwiran | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 3707 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 21-Apr-2023 | Actual Date of Completion (Capex): 08-Apr-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 30.14mtr/103.43mtr | Kheri Wiran | 29.404197 | 77.762458 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersilble | 800LPM/50Mtr | Kheri Wiran | 29.404197 | 77.762458 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 250KL/12Mtr | Kheri Wiran | 29.404197 | 77.762458 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI Pipe | 150 | 0.0155 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 3.947 | |
| 2 | HDPE | 75 | 0.592 | |
| 3 | HDPE | 90 | 0.212 | |
| 4 | HDPE | 110 | 0.532 | |
| 5 | HDPE | 160 | 0.587 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 712 |