| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 8360511 | Name of Scheme: Padia Nagla Mustahkam | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 4410 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 19-Sep-2023 | Actual Date of Completion (Capex): 28-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 29.46MTR/101.50MTR | PADIA NAGLA MUSTAHKAM | 29.074858 | 78.90027 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBEMERSIBLE PUMP | 650LPM/45MTR | PADIA NAGLA MUSTAHKAM | 29.074858 | 78.90027 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 200KL/12MTR | PADIA NAGLA MUSTAHKAM | 29.07493 | 78.900387 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7 DI PIPE | 125 | 0.0165 | OK |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE PN-6: CLASS PE-100 | 90 | 0.671 | OK |
| 2 | HDPE PIPE PN-6: CLASS PE-100 | 75 | 0.656 | OK |
| 3 | HDPE PIPE PN-6: CLASS PE-100 | 63 | 4.423 | OK |
| 4 | HDPE PIPE PN-6: CLASS PE-100 | 110 | 0.174 | OK |
| 5 | HDPE PIPE PN-6: CLASS PE-100 | 140 | 0.171 | OK |
| 6 | HDPE PIPE PN-6: CLASS PE-100 | 200 | 0.014 | OK |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 508 |