Project Completion Certificate (Ground Water)
Scheme ID: 8388453 Name of Scheme: SINGHUAMAU No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 3728 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 05-Mar-2023 Actual Date of Completion (Capex): 01-May-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24M/ 91.8M SINGHUAMAU 27.315614 80.196145
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.81 M³ per Min /45Mtr SINGHUAMAU 27.315614 80.196145
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 250KL/ 16 Mtr SINGHUAMAU 27.315752 80.196103
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 200 0.02056
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 2.670
2 HDPE Pipe PN-6, Class PE-100 75 1.134
3 HDPE Pipe PN-6, Class PE-100 90 0.923
4 HDPE Pipe PN-6, Class PE-100 110 1.675
5 HDPE Pipe PN-6, Class PE-100 125 1.985
6 HDPE Pipe PN-6, Class PE-100 160 0.238
7 HDPE Pipe PN-6, Class PE-100 200 0.607
HSC Connection
Sno. Total Nos.
1 475
Other Details
2.97
0.00
2.90
31-Jul-2025
02-Aug-2025