Project Completion Plan


Minutes of Meeting Date - 24-Jun-2025

Solar and instruments installation work in progress at OHTs. Assurance by firm- All OHTs- will be integrated and functional on portal by 10.07.2025. Verification of OHTs by 15.07.2025.


Minutes of Meeting Date - 24-Jun-2025

Data of 51 nos. OHTs are showing in Master Control Station at WTP. Solar and instruments testing & commissioning work in progress at remaining OHTs. Only one team is available at site. Assurance by firm- All 116 Nos. OHTs- will be integrated and functional on portal by 10.07.2025. Verification of OHTs by 15.07.2025.


Minutes of Meeting Date - 08-Jul-2025

Slow progress in functionality. Assurance by firm- All 116 Nos. OHTs- will be integrated and functional on portal by 10.07.2025. Verification of OHTs by 15.07.2025.


Minutes of Meeting Date - 15-Jul-2025

Slow progress in functionality. Assurance by firm- All 116 Nos. OHTs- will be integrated and functional on portal by 15.07.2025. Verification of OHTs by 25.07.2025.


Minutes of Meeting Date - 22-Jul-2025

The person who joined the meeting had no knowledge of information of automation related works. Notice to be issued. Remaining non-functional OHTs and 65 nos. OHTs having incorrect data will be calibrated and functional on portal by 31.07.2025.


Minutes of Meeting Date - 29-Jul-2025

Calibration of flowmeter is required. Remaining disconnected OHT and non-functional OHTs (65 nos.) will be calibrated and functional on portal with correct data by 10.08.2025.


Minutes of Meeting Date - 29-Jul-2025

Flowmeter Calibration work in progress. Remaining disconnected OHT and non-functional OHTs (65 nos.) will be calibrated and functional on portal with correct data by 15.08.2025.