      Dhoora Balabehat GOV (8134922)

Project Completion Plan


Minutes of Meeting Date - 29-Jul-2025

due to heavy flood in betwa river all path are block last 2 day no water supply in this scheme . . in 4 CWRs Due to the availability of regular power pending at Trees trimming/cutting at Van Nigam level, and DLM lalitpur assured that will be rectified by 30th of July, RTU,solar panel installation work is in progress at 3 nos OHT,and completed with in 05/08/25. after that complete integration along with data verification will be finalized within 01 week