From the last 3 months only Intake has been integrated and functional. 01 no. team is available at site. Assurance by firm- All OHTs will be integrated and functional on portal by 05.07.2025.
As per the instruction, notice regarding slow progress of automation & integration work is to be issued. Assurance by firm- 03 nos. team available at sites. Integration of WTP is in progress. All OHTs will be integrated and functional on portal by 05.07.2025.
As per the instruction, notice regarding slow progress of automation & integration work is to be issued. Assurance by firm- 03 nos. team available at sites. Integration of WTP is in progress. All OHTs will be integrated and functional on portal by 15.07.2025.
Notice regarding slow progress of automation & integration work is to be issued. Assurance by firm- now 03 nos. team available at site. All OHTs will be integrated and functional on portal by 25.07.2025. Micro plan need to be submit.
Integration work in progress. Assurance by firm- all 46 nos. OHT will be integrated and functional in one week on portal (by 25.07.2025). No micro plan submitted by firm.
Firm is not working seriously. Despite providing revised dates on a weekly basis, the work on site is not progressing accordingly. Notice is to be issued. Assurance by firm- all 46 nos. OHT will be integrated and functional in one week on portal (by 31.07.2025). No micro plan submitted by firm.