Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in
Check List Form

      Talar GOV (8152518)

Project Completion Plan


Minutes of Meeting Date - 05-Aug-2025

All OHT has been made functional on portal earlier . 1 OHT GPRS modam not working which would have been corrected till 30.7.25. Firm commited again to make it functional till 10.8.25 .


Minutes of Meeting Date - 19-Aug-2025

All OHT has been made functional on portal. Data are being hold as supply off . It was commited that EMF are being calibrated and same will be completed till 30.8.25.


Minutes of Meeting Date - 26-Aug-2025

All OHT has been made functional on portal . Firm commited that all instruments will be calibrated and integrated till 30.8.25. High value of RCA are being shown for which table has been generated . Same shall be completed with help of Sigma team.


Minutes of Meeting Date - 02-Sep-2025

All OHT has been made functional on portal . Firm commited that all instruments will be calibrated and integrated till 30.8.25. Reflection of High RCA value shall be resolve till 12.9.25.


Minutes of Meeting Date - 09-Sep-2025

All OHT has been made functional on portal . Firm commited that all instruments will be calibrated and integrated till 30.8.25. But Components instrument value are either constant or zero yet. Firm again committed to verify data till 15.9.25 also OHTs RCA value shall be updated till 15.9.25 .