All 48 OHT has been made functional on portal . Firm commited to calibrat 24 nos. installed instruments till 31.8.25 and remaining 24 nos. till 8.9.25 . Calibration work to be expedite .
All 48 OHT has been made functional on portal . Firm has to be calibrate and verify the data till 8.9.25 . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero .
All 48 OHT has been made functional on portal . Firm has to be calibrate and verify the data till 8.9.25 . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . Configuration are not being done . Firm again committed to complete the same till 30.9.25
All 48 OHT has been made functional on portal . Configuration are not being done . Firm again committed to complete the same till 30.9.25 . Data correction work are not being started causing non verification of data .
All 48 OHT has been made functional on portal . Intake well, WTP, OHT instruments data are constant . CWR instruments data are zero . Configuration are not being done . As per recommitment same should have completed till 30.9.25 . Firm again commite to expedite and complete the same till 12.11.25