Intake well, WTP, CWR SCADA commissioning work has been completed . It was committed that Intake well, WTP, CWRs SCADA commissioning work & it integration work would have been completed till 15.8.25 .
Intake well, WTP, CWR SCADA commissioning work has been completed . Firm committed again that Intake well, WTP, CWRs integration work will be completed till 10.9.25 . V set are being procured for Sites having network issue & same will be received at site till 6.9.25 .
Intake well, WTP, CWRs SCADA commissioning work & it integration work would have been completed till 10.8.25 and 18.8.25 respectively . But only intake SCADA commissioned . Firm again committed to complete commissioning of WTP , CWR OHT SCADA work with Integration till 25.9.25 .