| S. No. |
Nodal Officer Name |
District |
Inspection Date |
Scheme ID |
Scheme Name |
Village Name |
HGJ Certificaton Date(E-jalsakti) |
Agency Name/Phase |
Regular water supply Status |
Road Restoration (KM) |
OHT Progress Completed (%) |
FHTC |
Distribution (KM) |
Complaints |
Observation by Nodal Officer |
Instruction by ED (SWSM) |
Compliance Report |
Review by Nodal Officer |
| Target |
Completed |
Target |
Completed |
Target |
Completed |
Received |
Closed Complains |
Report |
Photograph |
| 1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
|
|
|
|
|
|
|
|
|
Total |
24.95 |
24.55 |
-- |
1482 |
1040 |
20.61 |
22.02 |
15 |
15 |
-- |
-- |
-- |
-- |
-- |
| 1 |
V K Singh |
Mainpuri |
21-Aug-2025 |
20037016 |
LEHRA GRAM PANCHAYAT WATER SUPPLY SCHEME |
Lehra |
04-Jan-2025 |
NCC Ltd. |
हाँ |
9.55 |
9.15 |
90.00% |
472 |
431 |
6.62 |
6.62 |
0 |
0 |
लहरा ग्राम पेयजल योजना की भौतिक प्रगति 75% है। वर्तमान में धनाभाव के कारण कार्य बाधित है। |
|
|
|
|
| 2 |
V K Singh |
Mainpuri |
21-Aug-2025 |
20012209 |
JAMTHARI WATER SUPPLY SCHEME |
Jamthari |
22-May-2024 |
NCC Ltd. |
हाँ |
9.40 |
9.40 |
95.00% |
735 |
392 |
9.49 |
9.40 |
8 |
8 |
जमथरी ग्राम पेयजल योजना की भाैतिक प्रगति 95 % हैा वर्तमान में धनाभाव के कारण कार्य बाधित है। |
|
|
|
|
| 3 |
V K Singh |
Mainpuri |
22-Aug-2025 |
20019046 |
NIJAMPUR GRAM PANCHAYAT WATER SUPPLY SCHEME |
Jaswantnagar |
22-Nov-2024 |
NCC Ltd. |
हाँ |
6.00 |
6.00 |
95.00% |
275 |
217 |
4.50 |
6.00 |
7 |
7 |
निजामपुर ग्राम पेयजल योजना की भौतिक प्रगति 95% है। वर्तमान में धनाभाव के कारण कार्य बाधित है। |
|
|
|
|