Total Record : 3
| S. No. | Nodal Officer Name | District | Inspection Date | Scheme ID | Scheme Name | Village Name | HGJ Certificaton Date(E-jalsakti) | Agency Name/Phase | Regular water supply Status | Road Restoration (KM) | OHT Progress Completed (%) | FHTC | Distribution (KM) | Complaints | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Target | Completed | Target | Completed | Target | Completed | Received | Closed Complains | |||||||||||
| Total | 11.92 | 11.92 | -- | 1546 | 1546 | 22.98 | 23.98 | 32 | 30 | |||||||||
| 1 | Sewa Lal | Bareilly | 29-Aug-2025 | 20012256 | BHADRAK WATER SUPPLY SCHEME | Bhadrak | 23-Aug-2024 | NCC Ltd. | हाँ | 2.90 | 2.90 | 100.00% | 373 | 373 | 6.40 | 6.90 | 8 | 8 |
| 2 | Sewa Lal | Bareilly | 28-Aug-2025 | 20038247 | Purainatal & Jafra | Purainatal | 06-Jun-2024 | NCC Ltd. | हाँ | 3.72 | 3.72 | 100.00% | 752 | 752 | 9.42 | 9.92 | 17 | 17 |
| 3 | Sewa Lal | Bareilly | 28-Aug-2025 | 20038431 | Kachnari | Kachnari | 25-May-2024 | NCC Ltd. | हाँ | 5.30 | 5.30 | 100.00% | 421 | 421 | 7.16 | 7.16 | 7 | 5 |