S. No. Nodal Officer Name District Inspection Date Scheme ID Scheme Name Village Name HGJ Certificaton Date(E-jalsakti) Agency Name/Phase Regular water supply Status Road Restoration (KM) OHT Progress Completed (%) FHTC Distribution (KM) Complaints Observation by Nodal Officer Instruction by ED (SWSM) Compliance Report Review by Nodal Officer
Target Completed Target Completed Target Completed Received Closed Complains Report Photograph
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Total 616.72 463.80 -- 2581 2539 251.77 251.45 170 148 -- -- -- -- --
1 Ravindra bahadur srivastava Chitrakoot 11-Jul-2025 8134609 Chandi Bangar GOV Kal Waliya 11-Jun-2024 Larsen & Toubro Ltd नहीं 0.60 0.45 0.00% 236 238 0.00 0.00 0 0 Many finishing works are balance and man power are not sufficient.
2 Ravindra bahadur srivastava Chitrakoot 11-Jul-2025 8134609 Chandi Bangar GOV Patwariya Sani 11-Jun-2024 Larsen & Toubro Ltd नहीं 0.57 0.21 0.00% 154 148 0.00 0.00 0 0 not satisfactory
3 Ravindra bahadur srivastava Chitrakoot 11-Jul-2025 8134609 Chandi Bangar GOV Dudauli Larsen & Toubro Ltd नहीं 602.00 450.00 0.00% 155 139 0.00 0.00 0 0 Progress is not satis factory
4 Ravindra bahadur srivastava Chitrakoot 11-Jul-2025 8134609 Chandi Bangar GOV Deval Larsen & Toubro Ltd नहीं 0.78 0.51 0.00% 346 215 0.00 0.00 0 0 not satisfactory, at some places road restoration found balance, no regular water supply, water works campus is incomplete and not developed. Required manpower is not sufficient.
5 Ravindra bahadur srivastava Chitrakoot 11-Jul-2025 8134609 Chandi Bangar GOV Sadh 11-Nov-2025 Larsen & Toubro Ltd नहीं 0.25 0.16 0.00% 43 36 0.00 0.00 0 0 Not satisfactory, balance woks to be completed earlier.
6 Ravindra bahadur srivastava Chitrakoot 10-Sep-2025 8134609 Chandi Bangar GOV Dubari 10-Oct-2024 Larsen & Toubro Ltd नहीं 1.04 1.04 95.00% 328 370 47.50 47.50 18 18 Not satisfactory,mostly fhtc having very low pressure. A lot of leakages found in distribution system.Some fhtc have no water supply since biggning of ater sipply.
7 Ravindra bahadur srivastava Chitrakoot 10-Sep-2025 8134609 Chandi Bangar GOV Gauri Mafi 03-Sep-2024 Larsen & Toubro Ltd नहीं 1.04 1.04 90.00% 47 47 47.00 47.00 18 18 88%,Some works are incomplete but no sufficient man power is avilable.
8 Ravindra bahadur srivastava Chitrakoot 10-Sep-2025 8134609 Chandi Bangar GOV Earan Mafi 16-Oct-2024 Larsen & Toubro Ltd नहीं 1.04 1.04 90.00% 103 103 47.50 47.50 22 20 90
9 Ravindra bahadur srivastava Chitrakoot 10-Jul-2025 8135453 Raipura GOV Karaunha 19-Nov-2024 GVPR नहीं 0.48 0.48 0.00% 342 342 0.00 0.00 0 0 Not satisfactory, very less man power are available at site.
10 Ravindra bahadur srivastava Chitrakoot 11-Sep-2025 8134589 Silauta Mustkil GOV Ghurehta 16-Apr-2024 Larsen & Toubro Ltd नहीं 1.63 1.58 95.00% 337 337 7.08 7.08 32 28 Satisfactory but much improvement in timely and regular water supply is required.
11 Ravindra bahadur srivastava Chitrakoot 11-Sep-2025 8134589 Silauta Mustkil GOV Amarpur 23-Apr-2024 Larsen & Toubro Ltd हाँ 1.63 1.63 95.00% 96 137 18.37 21.40 15 12 95%
12 Ravindra bahadur srivastava Chitrakoot 11-Sep-2025 8134589 Silauta Mustkil GOV Ram Tekawa 09-Jan-2024 Larsen & Toubro Ltd हाँ 0.83 0.83 100.00% 14 20 24.80 21.45 10 9 95
13 Ravindra bahadur srivastava Chitrakoot 11-Sep-2025 8134589 Silauta Mustkil GOV Ghunuwa 13-Apr-2024 Larsen & Toubro Ltd हाँ 1.61 1.61 100.00% 251 271 8.86 8.86 25 20 Satisfactory but some improvement is required
14 Ravindra bahadur srivastava Chitrakoot 11-Sep-2025 8134589 Silauta Mustkil GOV Bisaundha 13-Apr-2024 Larsen & Toubro Ltd नहीं 1.61 1.61 100.00% 122 122 25.33 25.33 25 20 Satisfactory but water supply timing and prper water pressure must be ensured.
15 Ravindra bahadur srivastava Chitrakoot 11-Sep-2025 8134589 Silauta Mustkil GOV TENDUWA KHURD 25-Feb-2025 Larsen & Toubro Ltd हाँ 1.61 1.61 100.00% 7 14 25.33 25.33 5 3 Satisfied