Physical Progress Phase-2, 3 & 5 |
||||
|---|---|---|---|---|
| Sr.No. | Components | Taget | Achivement | % |
| 1 | 2 | 3 | 4 | 5 |
| 1 | Tubewell | 38390 | 37991 | 98.96 |
| 2 | Pump House | 38390 | 37248 | 97.03 |
| 3 | OHT | 36460 | 35521/18206 | 97.42 |
| 4 | Distribution (Line Laying in Km.) | 450580 | 425612 | 94.46 |
| 5 | Solar Plant | 32870 | 28934 | 88.03 |
| 6 | HGJ Status | 72907 | 37091 | 50.87 |
| 7 | Comissioning of Village | 72907 | 45271 | 62.09 |
| 8 | ROAD DISMENTLING/RESTORATION(KM) | 181805 | 177149 | 97.44 |