Physical Progress Phase-2, 3 & 5 |
||||
|---|---|---|---|---|
| Sr.No. | Components | Taget | Achivement | % |
| 1 | 2 | 3 | 4 | 5 |
| 1 | Tubewell | 38318 | 37929 | 98.98 |
| 2 | Pump House | 38318 | 37132 | 96.90 |
| 3 | OHT | 36378 | 35749/17631 | 98.27 |
| 4 | Distribution (Line Laying in Km.) | 450118 | 424579 | 94.33 |
| 5 | Solar Plant | 32809 | 28794 | 87.76 |
| 6 | HGJ Status | 72213 | 35120 | 48.63 |
| 7 | Comissioning of Village | 72213 | 44386 | 61.47 |
| 8 | ROAD DISMENTLING/RESTORATION(KM) | 180389 | 175531 | 97.31 |