Physical Progress Phase-2, 3 & 5 |
||||
---|---|---|---|---|
Sr.No. | Components | Taget | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 38324 | 37919 | 98.94 |
2 | Pump House | 38324 | 37124 | 96.87 |
3 | OHT | 36384 | 35740/16902 | 98.23 |
4 | Distribution (Line Laying in Km.) | 450148 | 424073 | 94.21 |
5 | Solar Plant | 32815 | 28711 | 87.49 |
6 | HGJ Status | 72225 | 34428 | 47.67 |
7 | Comissioning of Village | 72225 | 43978 | 60.89 |
8 | ROAD DISMENTLING/RESTORATION(KM) | 178853 | 173911 | 97.24 |