Physical Progress Phase-2, 3 & 5 |
||||
---|---|---|---|---|
Sr.No. | Components | Taget | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 38330 | 37916 | 98.92 |
2 | Pump House | 38330 | 37071 | 96.72 |
3 | OHT | 36389 | 35722/16301 | 98.17 |
4 | Distribution (Line Laying in Km.) | 450423 | 423459 | 94.01 |
5 | Solar Plant | 32817 | 28669 | 87.36 |
6 | HGJ Status | 72115 | 33689 | 46.72 |
7 | Comissioning of Village | 72115 | 43565 | 60.41 |
8 | ROAD DISMENTLING/RESTORATION(KM) | 178370 | 174195 | 97.66 |