| S.No. | Scheme ID | Scheme Name | OHT Code | Non-Compliance | Compliance(Current Status) | Description
|
||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Major Honey Comb | Alignment | Cube Test | Exposure | Deviation | Tank Observation | Other | SBC Issue | Demolish Partially | Demolish Fully | Under Examination | Serious Observation | Water Body | Compliance Major Honey Comb | Compliance Alignment | Compliance Cube Test | Compliance Exposure | Compliance Deviation | Compliance Tank | Compliance Other | Compliance SBC Issue | Compliance Demolish Partially | Compliance Demolish Fully | Compliance Under Examination | Compliance Serious Observation | Compliance Water Body | |||||
| 1 | 20092850 | BISHUNAPUR RAMNAGAR | 20092850/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | 1- Major honeycombing is visible in the overhead tank's 2nd and 3rd brace beam junction and steel are visible at junction. 2- Over Head tank work stopped for a long time. | |||||||||||||
| 2 | 20089731 | MANIHAR TARA | 20089731/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Honeycombing has been observed in the first brace and column of the overhead tank, indicating poor compaction and inferior quality of concrete. These deficiencies may reduce the structural strength and durability of the overhead tank, and immediate corrective measures are required. | |||||||||||||
| 3 | 20092764 | BARGADAHA | 20092764/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | the paint finishing is not correct, plinth protection is creak, second brace has been minor honeycombs. | |||||||||||||
| 4 | 20097256 | SONBARSA | 20097256/01 | No | No | No | No | No | No | No | No | No | No | No | No | No | 1. Miner honeycomb are visible in over Head tank stairs and poor workmanship observed. 2. Over Head tank column and brace Finishing work required | |||||||||||||
| 5 | 20097264 | DIKRA | 20097264/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | 1. Honeycombing has been observed in the second brace of the OHT, where the reinforcement steel is exposed. 2. Similar honeycombing is also observed in the column, with reinforcement steel visible. 3. These deficiencies indicate poor concrete compaction and inadequate cover, which may adversely affect the structural strength and durability of the OHT. | |||||||||||||
| 6 | 20088918 | BELHA RAGHAV | 20088918/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | 1. Honeycomb are visible in 3rd brace and bottom ring beam and finishing work required in top slab of over Head tank | |||||||||||||
| 7 | 20097282 | PARAS RAMPUR_ BISUNAPUR | 20097282/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | 1. Brace beams and Column of OHT show noticeable misalignment.. | |||||||||||||
| 8 | 20100192 | GANDHI | 20100192/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. The project was halted for some time and vertical reinforcement bars of all five columns were cut from the bottom may leads to structure durability & stability failures. | |||||||||||||
| 9 | 20093092 | JAGRAWAL GARHI | 20093092/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. The project was halted for some time and vertical reinforcement bars of all five columns were cut from the bottom may leads to structure durability & stability failures. | |||||||||||||
| 10 | 20088895 | GODARI | 20088895/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. The project was halted for some time and vertical reinforcement bars of columns were cut from the bottom may leads to structure durability & stability failures. | |||||||||||||
| 11 | 20089758 | ETAUNJHA_BARAIPUR | 20089758/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. The steel is rusted,ensure that all rusted steel reinforcement is propley cleaned or repleced prior to further work . 2. No concreting or febrication shall proceed until corrective action are taken. | |||||||||||||
| 12 | 20088951 | SHAHPUR PURE SHIVDIN | 20088951/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1.Reinforcement has been cut and stolen from the column of OHT due to stoppage of construction activities at site more than 6 month ago. 2-Reinforcement bars have been correded. | |||||||||||||
| 13 | 20088901 | RANIPUR QUAZI | 20088901/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. The project was halted for some time and vertical reinforcement bars of columns were cut from the bottom may leads to structure durability & stability failures. | |||||||||||||
| 14 | 20097241 | HEMPUR | 20097241/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. Water has been accumulating in the OHT campus for the past 12 months due to lack of soil backfiJling inside the campus and absence of a proper drainage system. 2. This prolonged waterlogging can weaken the soil, affect foundation stability, cause corrosion of metal components, damage concrete surfaces, and reduce the durability of the structure, even though all OHT works-including Fu ll staging-have been completed. 3. lt is observed that staircases reinforcement steel cut/removed from the waist slab, tread and riser and landing ancho rage. | |||||||||||||
| 15 | 20088952 | TANDUWA RATANPUR | 20088952/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1- lt is observed that staircases R/F steel cut/removed from the waist slab, tread and riser and landing. a nchorage. 2- !t is obserr.,ed that Cracks are seen in boundar;, wall. 3- Over Head tank column 3rd brace brace steel was rusted due to No work ongoing in the last 1year. 4 Due to the prolonged suspension of construction, activities steel Found Corroded which may affect the durability & stability of the structure. | |||||||||||||
| 16 | 20088899 | KATHA | 20088899/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. The steel is rusted,ensure that all rusted steel reinforcement is propley cleaned or repleced prior to further work . 2. No concreting or febrication shall proceed until corrective action are taken. | |||||||||||||
| 17 | 20093299 | GANGAPUR_SENAURA TARAI | 20093299/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. The sieel rusted in the Column up to 13t brace beam ofthe overhead tank. 2- Due to the prolonged suspension of construction activities steel Found Corroded which may affect the durability & stability ofthe structure. | |||||||||||||
| 18 | 20092879 | AMARAHWA | 20092879/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1- lt is observed that staircases reinforcement steel cut/removed from the waist slab, tread and riser and landing anchorage. 2- Over Head tank work stopped in the last year and stajrs steel and 3rd brace above cotumn steelwas found rusted at site. | |||||||||||||
| 19 | 20093100 | TITIHIRIRA | 20093100/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1- Miner honeycomb found in stairs and over Head tank 3rd brace above column steel rusted. 2- Over Head tank work stopped for a long time. 3-lt is observed that Column above 3rd brace and staircase steel rusted found at site. | |||||||||||||
| 20 | 20097263 | MAHADEWA | 20097263/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. The work has been suspended for a prolonged period. 2. Due to prolonged exposure and lack of protective measures, corrosion of the reinforcement steel has been observed in the columns and staircase members. | |||||||||||||
| 21 | 20088914 | RAJAPUR RANI | 20088914/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. over Head tank column steel was fully rusted due to work stopped since Long time and one stairs steel cutting. | |||||||||||||
| 22 | 20092940 | MANWARIYA BOJHA | 20092940/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. The reinforcement above the GL at the staircase has been cut, and the steel is completely rusted. 2. In the cylindrical wall, the first lift casting was done a long time ago, but the second lift casting has not yet been carried out. 3. The exposed steel reinforcement is heavily rusted. | |||||||||||||
| 23 | 20097126 | Tilakpur W/S | 20097126/01 | No | No | No | No | No | No | No | No | No | No | No | No | No | 1.The project was halted for some time and vertical reinlorcement bars of all five columns were cut from the bottom may leads to structure durability & stability failures. | |||||||||||||
| 24 | 20088892 | DIKAULI | 20088892/01 | No | No | No | No | No | No | No | No | Yes | No | No | No | No | 1. Leake observed in bottom dome RRC water tank. | |||||||||||||
| 25 | 20088912 | TULSIPUR | 20088912/01 | No | No | No | No | No | Yes | No | No | No | No | No | No | No | 1. Regarding Leakage has been observed at multiple locations in the overhead tank, indicating inadequate waterproofing and poor workmanship. | |||||||||||||
| 26 | 20097287 | ACHARAURA SHAHPURA_ ASNI | 20097287/01 | No | No | No | No | No | No | No | No | Yes | No | No | No | No | 1. Seepage has been observed in the bottom dome of the Overhead Water Tank . | |||||||||||||
| 27 | 20089749 | LUXMANPUR GORPURWA_GANESHPUR | 20089749/01 | No | No | No | No | No | No | No | No | Yes | No | No | No | No | 1. Seepage in observed in over Head tank bottom dome and poor workmanship observed in brace junction and finishing work required in 2nd brace. | |||||||||||||
| 28 | 20088935 | MAHDEIYA | 20088935/01 | No | No | No | No | No | No | No | No | Yes | No | No | No | No | 1. Critically Water leakage has been observed from several points in bottom dome of OHT it is recommended kindly fill water in tank after rectification work and DI pipe also leakaging. | |||||||||||||
| 29 | 20093247 | RAMPUR_LAKSHAMANPUR GANGAPUR | 20093247/01 | Yes | No | No | No | No | No | No | No | Yes | No | No | No | No | 1. The bottom dome beams of the OHT have honeycombing, and it has been several days since the last flight ofthe staircase was costed, but the de-suturing has not been done yet. | |||||||||||||
| 30 | 20100189 | KHAIRY TARAI | 20100189/01 | No | No | No | Yes | No | No | Yes | No | No | No | No | No | No | 1. The project was halted for some time and vertical reinforcement bars of all five columns were cut from the bottom and water logging is under OHT. | |||||||||||||
| 31 | 20097324 | RAMNAGAR CHIRADIH | 20097324/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | 1. The project was halted for some time and vertical reinforcement bars of all five columns were cut from the bottom may leads to structure durability & stability failures. | |||||||||||||
| 32 | 20089740 | DAHAVER KALAN_BHOJPUR | 20089740/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | 1.Major Honeycomb observed during site visit in 1st brace beam. | |||||||||||||
| 33 | 20092698 | PURUSHOTTOMPUR | 20092698/01 | No | No | No | No | No | No | No | No | Yes | No | No | No | No | 1. Leakage/seepage observed in OHT bottom dome. | |||||||||||||
| 34 | 20093115 | HARIHARPUR MAHRAJ NAGAR | 20093115/01 | Yes | Yes | No | No | No | No | No | No | No | No | No | No | No | 1. Second breace beam is not alignment,finshing of staire is very poor quality, 2. Honeycomb has been found at Top dome. | |||||||||||||
| 35 | 20074445 | RAMWAPUR | 20074445/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | 1. Cover blocks are not placed properly. 2. Proper safety not maintained by the manpower at site. 3. PPE kit are not available for manpower at site. 4. Weight batcher are not available at site., 5. Vibrator & compaction not done properly & Cube mould was not available on site as per requirement. | |||||||||||||
| 36 | 20097302 | MADRAHVA_ BELHARI | 20097302/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | No | No | 1. Brace beams of OHT show noticeable misalignment. Cracks have been observed in the platform of stairs. | |||||||||||||
| 37 | 20093343 | BHIKHPUR TARAI_BENI DIHUA | 20093343/01 | Yes | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | 1. Honeycombing has appeared in several sections of the bottom ring beam, and in many places, the stirrups of the ring beam are fully exposed; this condition could potentially compromise the structural integrity of the bottom ring beam in the future. 2. Please ensure that this work is rectified as a matter of utmost urgency. 1. Cube Test failed for Column above 2nd Brace Beam (28 Days) during compressive strength test in GP-Bhikpur Tarai पत्रांक संख्या: 1085 / VPL /HYD/SBT/2025-26 दिनांक: 23/07/2025 | ||||||||||||
| 38 | 20088945 | JOGIN BHARIYA | 20088945/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | 1.Cube Test failed of OHT Column above 2nd brace beam during compressive strength test. पत्रांक संख्या: - 1125 / VPL /HYD/SBT/2025-26 दिनांक- 13/08/2025 | ||||||||||||
| 39 | 20092984 | SHRI NAGAR | 20092984/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | 1. Honeycomb has been observed in second brace of OHT. पत्रांक संख्या: - 1135 / VPL /HYD/SBT/2025-26 दिनांक- 19/08/25 | ||||||||||||
| 40 | 20093199 | JHIRJHIRAWA | 20093199/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | The casting of Raft foundation has been done in late night on 19-06-2025 and heavy rain occurred after concreting work due to which concrete of raft submerged under water within 4 hours of pouring, it can pose serious risks to the strength, durability, and integrity of the structure due to the disruption of the initial setting and hydration process of cement. पत्रांक संख्या: 1086 / VPL /HYD/SBT/2025-26 दिनांक- 23/07/2025 | ||||||||||||
| 41 | 20093126 | PATPAR GANJ_BABHAN PURWA | 20093126/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | 1. Honeycomb has been observed at brace beam and at joint of stairs with column. 2. Crack has been observed in platform of stairs. पत्रांक संख्या: 1089 / VPL /HYD/SBT/2025-26 दिनांक- 23/07/25 | ||||||||||||
| 42 | 20092749 | PIPRAHWA JOGA GAON | 20092749/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | 1. Honeycomb is found in oht 1st brace. पत्रांक संख्या: 1330 / VPL /HYD/SBT/2025-26 दिनांक- 20/11/2025 | ||||||||||||
| 43 | 20092951 | MADHVAPUR | 20092951/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | 1. Honeycomb found in 3rd brace. पत्रांक संख्या: 1087 / VPL /HYD/SBT/2025-26 दिनांक- 23/07/25 | ||||||||||||
| 44 | 20074384 | RAMPUR KAKRA | 20074384/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The project was halted for some time and vertical reinforcement bars of columns were cut from the bottom may leads to structure durability & stability failures. पत्रांक संख्या: 1328 / VPL /HYD/SBT/2025-26 दिनांक- 20/11/2025 | ||||||||||||
| 45 | 20074610 | ETWARIYA | 20074610/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The project was halted for long time and reinforcement bars have been corroded which may leads to structure durability & stability failures. पत्रांक संख्या: 1090 / VPL /HYD/SBT/2025-26 दिनांक- 23/07/25 | ||||||||||||
| 46 | 20088924 | CHAINPUR | 20088924/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The project was halted for long time and reinforcement bars have been corroded which may leads to structure durability & stability failures. पत्रांक संख्या: 1090 / VPL /HYD/SBT/2025-26 दिनांक- 23/07/25 | ||||||||||||
| 47 | 20089735 | VIJAYPUR SISAWAN | 20089735/01 | No | No | No | Yes | No | No | Yes | No | No | No | No | No | No | Resolved | Resolved | 1. Rusted steel was used and material test was not done before casting. No RFI raised and no information given before casting. पत्रांक संख्या: 1660 / VPL /HYD/SBT/2025-26 दिनांक- 23/04/2026 2. The project was halted for long time and reinforcement bars have been corroded which may leads to structure durability & stability failures. पत्रांक संख्या: 1384/ VPL /HYD/SBT/2025-26 दिनांक- 08/12/2025 | |||||||||||
| 48 | 20088948 | SAMHAR PURAWA | 20088948/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The project was halted for long time and reinforcement bars have been corroded which may leads to structure durability & stability failures. पत्रांक संख्या: 1082 / VPL /HYD/SBT/2025-26 दिनांक- 23/07/25 | ||||||||||||
| 49 | 20093335 | PIPRAHAWA_BAHADURPUR | 20093335/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The project was halted for long time and reinforcement bars have been corroded which may leads to structure durability & stability failures. पत्रांक संख्या: 1083 / VPL /HYD/SBT/2025-26 दिनांक- 23/07/25 | ||||||||||||
| 50 | 20088894 | GILAULI | 20088894/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The project was halted for long time and reinforcement bars have been corroded which may leads to structure durability & stability failures. Letter Number: 1165 VPL /HYD/SBT/2025-26 Date: 30/08/25 | ||||||||||||
| 51 | 20088947 | PATKHAULI | 20088947/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1. Material test was not done before casting. No RFI raised and no information given before casting. Letter Number: 1234 VPL /HYD/SBT/2025-26 Date: 20/09/2025 | ||||||||||||
| 52 | 20097127 | Kevalpur W/S | 20097127/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The stirrup provided in OHT slab beam BT1,BT2 and the ring beam have hook lengths rainnig from 40mm to 50mm which is not as per approval drwaing. 2. Some of the strupes hooks in the OHT slab beam have been bent at a 90-degree angle, whereas the approval drwaing specify a hook bend angale of 135-degree. Letter Number: 1143 / VPL /HYD/SBT/2025-26 Date: 22/08/2025 | ||||||||||||
| 53 | 20093189 | MANSUKHA_KALYANPUR | 20093189/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. Due to the prolonged suspension of construction activities steel found Corroded which may affect the durability& stability of the structure. Letter Reference Number: 1327/VPL/HYD/SBT/2025-26 Date: 20/11/2025 | ||||||||||||
| 54 | 20088956 | BHOWSAWAN_KURBENI | 20088956/01 | Yes | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | Resolved | 1. Major Honeycomb was found in 2nd and 3nd brace beam,Rinforcement has been visible on surface of top dome opening, 2. Due to prolonged suspension of construction activities steel found corroded which may affect the durability & stability of structure. Letter Number: 1315/VPL/HYD/SBT/2025-26 Date: 14/11/2025 | |||||||||||
| 55 | 20097250 | LALPUR AYODHYA | 20097250/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. Due to the prolonged suspension of construction activities steel found Corroded which may affect the durability& stability of the structure. Letter Number: 1374/VPL/HYD/SBT/2025-26 Date: 05/12/2025 | ||||||||||||
| 56 | 20074430 | JORDIH | 20074430/01 | Yes | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | Resolved | 1. Major Honeycomb was found in 3rd and 2nd flight beam on stairs. 2. Reinforcement has been visible on the surface of 3rd flight beam on stairs due to poor workmanship. 3. Major Honeycomb was found in 3rd brace beam. Letter Number: 1316/VPL/HYD/SBT/2025-26 Date: 14/11/2025 | |||||||||||
| 57 | 20074435 | MAHADEO JAGDISH | 20074435/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The steel is rusted,ensure that all rusted steel reinforcement is propley cleaned or repleced prior to further work No concreting or febrication shall proceed until corrective action are taken. Letter Number: पत्रांक संख्या: 1329/VPL/HYD/SBT/2025-26 Date- 20/11/25 | ||||||||||||
| 58 | 20074413 | MUJHANIYA | 20074413/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The steel is rusted,ensure that all rusted steel reinforcement is propley cleaned or repleced prior to further work 2. No concreting or febrication shall proceed until corrective action are taken. पत्रांक संख्या: 1373 / VPL / HYD / SBT / 2025-26 Date:- 05/12/2025 | ||||||||||||
| 59 | 20075953 | ALI NAGAR DHARAN NAGAR | 20075953/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The steel is rusted,ensure that all rusted steel reinforcement is propley cleaned or repleced prior to further work 2. No concreting or febrication shall proceed until corrective action are taken. Letter Number:-1332 / VPL / HYD / SBT / 2025-26 Date: - 20/11/2025 | ||||||||||||
| 60 | 20097262 | BAHORWA | 20097262/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The steel is rusted,ensure that all rusted steel reinforcement is propley cleaned or repleced prior to further work 2. No concreting or febrication shall proceed until corrective action are taken. Letter Number:-1320 / VPL / HYD / SBT / 2025-26 Date:- 17/11/25 | ||||||||||||
| 61 | 20092861 | BIRPUR | 20092861/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The steel is rusted,ensure that all rusted steel reinforcement is propley cleaned or repleced prior to further work 2. No concreting or febrication shall proceed until corrective action are taken. Letter Number:- 1385 / VPL / HYD / SBT / 2025-26 Date: - 08/12/2025 | ||||||||||||
| 62 | 20074373 | KAKARDARI | 20074373/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. OHT Work is stopped from last 22 months after attending column up to 1 brace beam level. 2. Due to the prolonged suspension of construction activities column steel Found Corroded which may affect the durability & stability of the structure. The main reinforcement in the OHT column has not been lapped as specified within the designated lapping zone according to the approved design and drawings. Letter Number:- 1649 / VPL / HYD / SBT / 2026-27 Date:- दिनांक- 23/04/2026 | ||||||||||||
| 63 | 20097240 | DURGAPUR KP | 20097240/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. The steel is rusted,ensure that all rusted steel reinforcement is propley cleaned or repleced prior to further work 2. No concreting or febrication shall proceed until corrective action are taken. Letter Number:- 1441 / VPL / HYD / SBT / 2025-26 Date: - 08/01/2026 | ||||||||||||
| 64 | 20097128 | Rajapur Birpur W/S | 20097128/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. lt is observed that staircase steel rusted found at site. Letter no 1471 / VPL /HYD/SBT/2025-26 Date : 29/01/2026 | ||||||||||||
| 65 | 20092885 | SONPUR KALAN | 20092885/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1. OHT work has been completed up to GL level. However, the work has been stopped for a long period. Due to prolonged stoppage of work, rusting has been observed on the reinforcement steel of columns above GL level. Letter no 1662 / VPL /HYD/SBT/2026-27 Date: 28/04/26 | ||||||||||||
| 66 | 20074376 | KHAJUHA JHUNJHUNIA | 20074376/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | 1. During inspection, honeycombing was observed at various flights of the staircase of the Overhead Tank (OHT), indicating inadequate concrete compaction and poor workmanship. Water logging was also noticed due to insufficient drainage, which may lead to durability issues. 1. Additionally, one of the second braces was found to be executed with improper dimensions and is not in conformity with the approved drawings and design specifications also minor honeycomb at junction of column and ringbeam. Letter no 1679 / VPL /HYD/SBT/2026-27 Date 06/05/26 | ||||||||||||
| 67 | 20088929 | MOHMMADPUR RAJA | 20088929/01 | No | No | No | No | No | No | No | No | Yes | No | No | No | No | Resolved | 1. Critically Water leakage has been observed from several points in bottom dome of OHT. Letter no 1630 / VPL /HYD/SBT/2026-27 Date 15/04/26 | ||||||||||||
| 68 | 20093351 | KUNDA | 20093351/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1. Crack beam has been observed ring beam of OHT crack has been seen in balkani clamp has been not provided di pipe. Letter no 1602 / VPL /HYD/SBT/2025-26 Date 20/03/2026 | ||||||||||||
| 69 | 20074379 | MAKSRIHVA | 20074379/01 | Yes | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | Resolved | 1. Major Honeycomb was observed in the columns and braces of the overhead tank in Hariharpur Rani Gram Panchayat block, and the first brace has suffered minor damage. 2. The steel reinforcement for the bottom dome was installed 5 months ago, but the concrete casting has not yet been done, resulting in severe rusting of the steel in the bottom dome. 3. Poor workmanship was also observed in several areas of the overhead tank. Letter no 1678 / VPL /HYD/SBT/2026-27 Date: 06/05/26 | |||||||||||
| 70 | 20097280 | TENDWA MAHANT | 20097280/01 | Yes | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | Resolved | 1. Staircase steel found rusted and minor honeycomb found in balcony slab. Letter no 1631 / VPL /HYD/SBT/2026-27 Date: 15/04/26 | |||||||||||
| 71 | 20074370 | JANKI NAGAR | 20074370/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1. Plinth protection is being constructed for the OHT, in which PPC cement is being used. 2. The bricks for the side drain at the plinth level are being laid without conducting any tests. Letter no 1556 / VPL /HYD/SBT/2025-26 Date: 27/02/2026 | ||||||||||||
| 72 | 20088900 | RAMNAGARA | 20088900/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1. Raft casting of the OHT is in progress, and the concrete is being mixed using a manual mixture machine instead of weight batcher mixing machine. Also, the vibrator is not being operated properly. Letter Number: 1668 / VPL / HYD / SBT / 2026-27 Date: 02 / 05 / 2026 | ||||||||||||
| 73 | 20092891 | DARE KUIEYA | 20092891/01 | No | No | No | No | No | No | No | No | Yes | No | No | No | No | Resolved | 1. seepage observed in OHT bottom dome. Letter Number: 1670 / VPL / HYD / SBT / 2026-27 Date: 02 / 05 / 2026 | ||||||||||||
| 74 | 20092973 | IMALIYA KARANPUR | 20092973/01 | No | No | No | No | No | No | No | No | Yes | No | No | No | No | Resolved | 1. seepage observed in OHT bottom dome. Letter Number: 1669 / VPL / HYD / SBT / 2026-27 Date: 02 / 05 / 2026 | ||||||||||||
| 75 | 20097271 | SEMRI CHAK PIHANI | 20097271/01 | No | No | No | No | No | No | No | No | Yes | No | No | No | No | Resolved | 1. Seepase has been observed under the bottom dome of OHT , Crecke found in boundray wall. Letter Number : 1176 / VPL / HYD / SBT / 2025-26 Date: 05 / 09 / 2025 | ||||||||||||
| 76 | 20092870 | SANGRAMGANJ | 20092870/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | 1.Cube Test failed for 3rd Brace Beam (28 Days) during compressive strength test in GP-Sangramganj. Letter Number: 055 / VPL / HYD / SBT / 2025-26 Date: 09 - 06 - 2025 | ||||||||||||
| 77 | 20097283 | LAKHNA | 20097283/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | 1.Cube Test failed for raft of OHT (28 Days) during compressive strength test in GP-Lakhna. Letter Number): 860 / VPL / HYD / SBT / 2025-26 Date: 09 / 06 / 2025 | ||||||||||||
| 78 | 20088944 | CHAILAHI | 20088944/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | 1. Cube Test failed for raft concreting of OHT (28 Days) during compressive strength test. Letter Number: 860 / VPL / HYD / SBT / 2025-26 Date: 09 / 06 / 2025 | ||||||||||||