| S.No. | Scheme ID | Scheme Name | OHT Code | Non-Compliance | Compliance(Current Status) | Description
|
||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Major Honey Comb | Alignment | Cube Test | Exposure | Deviation | Tank Observation | Other | SBC Issue | Demolish Partially | Demolish Fully | Under Examination | Serious Observation | Water Body | Compliance Major Honey Comb | Compliance Alignment | Compliance Cube Test | Compliance Exposure | Compliance Deviation | Compliance Tank | Compliance Other | Compliance SBC Issue | Compliance Demolish Partially | Compliance Demolish Fully | Compliance Under Examination | Compliance Serious Observation | Compliance Water Body | |||||
| 1 | 20023430 | SOHASA SUMALI GP WSS | 20023430/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | OHT slab finishing with chipping and plastering work is done | ||||||||||||
| 2 | 20075102 | HASAUDI AVSANPUR GP WSS | 20075102/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | NDT Test is conducted result found satisfactory . | ||||||||||||
| 3 | 20021743 | Tanuhar Urf Khalilwaliya | 20021743/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | OHT slab conducted NDT test & result found satisfied. | ||||||||||||
| 4 | 20023331 | SANGRAM PUR GP WSS | 20023331/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | OHT 1st Brace Conducted NDT test & result found satisfied. | ||||||||||||
| 5 | 20075247 | MAJHAWAN KALA GP WSS | 20075247/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | OHT 3rd lift column above 2nd brace beam conducted NDT test & result found satisfied. | ||||||||||||
| 6 | 20021713 | Jahda Musthakam | 20021713/01 | No | No | No | No | No | Yes | No | No | No | No | No | No | No | Resolved | Water leak rectified and provide anode bag completed | ||||||||||||
| 7 | 20021823 | Mahua Pathak | 20021823/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | NDT test & result found satisfied. | ||||||||||||
| 8 | 8362767 | POKHAR BHITWA GP WSS | 8362767/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Regarding Honeycomb in OHT ring beam | |||||||||||||
| 9 | 20096892 | ROINHAWA GROUP OF GP WSS | 20096892/01 | No | No | No | No | No | Yes | No | No | No | No | No | No | No | Gap found between slab and tank Slab is not in level | |||||||||||||
| 10 | 8362151 | HATHIWAD TAAL GP WSS | 8362151/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Column lapping zone and alignment issue | |||||||||||||
| 11 | 8362951 | BARGO GP WATER SUPPLY SCHEME | 8362951/01 | No | No | No | No | No | No | No | No | No | No | No | No | No | 1. During site visit it is found that staircase dowel bar is cut. 2. Site is situated at low land area. It is advised to prefer boundary wall and pump house drawing in column beam. It is advised to TKC rectify the work | |||||||||||||
| 12 | 20029207 | BABHANI LAGARI GP WSS | 20029207/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Precast OHT dowel bar used different size of Bar. | |||||||||||||
| 13 | 20021827 | BASAWANPAKAR URF MADRAHIYA | 20021827/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | It has been observed that during column reinforcement (1 Nos. longitudinal bars), the required lap length of 1.50 m has not been provided (1.25 m provided) within the designated lapping zone as per IS 456:2000, which may adversely affect proper bond development and load transfer in the column. ATR submitted on 19.05.2026 | ||||||||||||
| 14 | 20015996 | BASAUNI | 20015996/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | OHT column first lift cube failure 7 - days.and Cube has been tested on 28 days result found satisfactory | ||||||||||||
| 15 | 20021620 | Dokam amya | 20021620/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | cube failure of 1st and 2nd Brace beam and After NDT test Conducted result found satisfactory. | ||||||||||||
| 16 | 20016001 | Badahar Ghat | 20016001/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Rectification done Removing the Rusted steel of Raft and rest of steel used iron oxide before casting. | ||||||||||||
| 17 | 20075136 | PARSOHAN GP WSS | 20075136/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | Concrete cube failed of OHT ring beam and cross beam below slab 28 days of testing and After NDT result found satisfactory. | ||||||||||||
| 18 | 20015987 | Shivpati Nagar | 20015987/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | 28 Days cube compressive strength test has been done & found satisfactory. | ||||||||||||
| 19 | 20036638 | KAPIYA MISHRA GP WSS | 20036638/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | Rebound hammer test done in 1st BB lift found satisfactory. | ||||||||||||
| 20 | 20075133 | HISANUDDIN PUR WSS | 20075133/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | Concrete Cube failed of OHT raft and Plinth beam of 28bday and after NDT test result found satisfactory . | ||||||||||||
| 21 | 20023361 | CHANNAR GADDI GP WSS | 20023361/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | Rebound hammer test done in col 1st lift found satisfactory. | ||||||||||||
| 22 | 20022651 | MAJHARI | 20022651/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | OHTcol 1st lift and raft cube failure of 28- days. and After NDT Test result found Satisfactory. | ||||||||||||
| 23 | 20016002 | Dewra Bazar | 20016002/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | OHT raft NDT has been done and test result found satisfactory | ||||||||||||
| 24 | 20023232 | MAHUI GP WSS | 20023232/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Construction of OHT Stair case trade and riser size issue. ATR Submitted on 19.05.2026. | ||||||||||||
| 25 | 20017615 | Lamui Tall GP Water supply scheme | 20017615/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | NDT test & result found satisfied. | ||||||||||||
| 26 | 20059873 | PADARIYA GP WSS | 20059873/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | NDT test & result found satisfied. | ||||||||||||
| 27 | 20036610 | TIWARIPUR EAST GP WSS | 20036610/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | Raft NDT test & result found satisfied. | ||||||||||||
| 28 | 20012549 | Para Nankar G.P. Water Supply Scheme | 20012549/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | OHT Raft Conducted NDT test & result found satisfied. | ||||||||||||
| 29 | 20075271 | DUBAI AND MUJDIH GP WSS | 20075271/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Comlun provide lap as per drawing within lapzone | ||||||||||||
| 30 | 20074947 | Ahiroli padri wss | 20074947/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | reinforcement and layout as per drawing | ||||||||||||
| 31 | 20075242 | JAGDISHPUR GRANT GP WSS | 20075242/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Repairing done honeycombing area | ||||||||||||
| 32 | 20021816 | BABHNI | 20021816/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | OHT 1st Brace beam and column above 1st brace beam Repairing done with injection grouting. | ||||||||||||
| 33 | 20020496 | Teknaar WS scheme | 20020496/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycomb at 2nd brace meam. ATR is submitted on 19.05.2026 | ||||||||||||
| 34 | 20096407 | DEKHARI GP WSS | 20096407/01 | No | No | No | No | No | No | No | No | No | No | No | No | No | OHT 1st brace Honeycomb found. Honeycomb is repaired with GP2 after that NDT (UPV and Rebound Hammer) is conducted in presence of UPJN & TPIA. reports found satisfactory. | |||||||||||||
| 35 | 20075254 | LUCHUYA GP WSS | 20075254/01 | No | No | No | No | No | No | No | No | No | No | No | No | No | Honeycomb found due to poor formwork and poor concrete compaction in Stair case. Honeycomb is repaired with GP-2 and NDT (UPV & Rebound hammer) is conducted in presence of UPJN and TPIA. report found satisfactory. | |||||||||||||
| 36 | 20075207 | SEMRIYAON GP WSS | 20075207/01 | No | No | No | No | No | No | No | No | No | No | No | No | No | OHT slab 28 days cube test is not found satisfactory. NDT is recommended. NDT test (UPV and Rebound hammer) test is conducted in presence of UPJN and TPIA an result found satisfactory. | |||||||||||||
| 37 | 20016124 | Bhagta WSS | 20016124/01 | No | No | No | No | No | Yes | No | No | No | No | No | No | No | 1. During site visit water leakage observed at the bottom periphery of zinc-alum tank. Water marks are visible on the concrete base near tank joints, indicating seepage from tank panel joints / bottom sealing. 2. It is also observed water seepage in bottom slab are seepage marks clearly evident on the slab surface.. 3. Uv foam sealing has not been provided at the bottom of the zinc-alum tank . | |||||||||||||
| 38 | 20020745 | BACHADA BACHADI GP WATER SUPPLY SCHEME | 20020745/01 | No | No | No | No | No | No | No | No | No | Yes | No | No | No | 1. Hydro-test of Zn-Al tank work is in progress without RFI and without supervision of manufacturer-engineer 2. During site visit it is found that thrust block of inlet , outlet ,Overflow , washout pipes are not made at site due to this total weight of pipe is carried out by Zn-Al tank this weight can damage the tank wall. | |||||||||||||
| 39 | 20016023 | Semari | 20016023/01 | No | No | No | No | No | No | No | No | No | No | No | Yes | No | 1. During site visit it is found that there is level difference in OHT slab panel .There is a chance of differential settlement of pre-cast slab panel after filling the tank with water. 2. Thrust block of inlet , outlet ,Overflow , washout pipes are not made at site due to this total weight of hanging pipe is carried out by Zn-Al tank this weight can damage the tank wall. | |||||||||||||
| 40 | 20058682 | KOLHUI GP WSS | 20058682/01 | No | No | No | No | No | No | No | No | No | No | No | Yes | No | 1. During site visit it is found that water is seepage through bottom of tank. 2. OHT Slab grouting of DI pipes is not done. Thrust block of inlet , outlet ,Overflow , washout pipes are not made at site due to this total weight of hanging pipe is carried out by Zn-Al tank this weight can damage the tank wall. | |||||||||||||
| 41 | 20023343 | BIRDPUR NO 5 GP WSS | 20023343/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | 1.During cube testing in MEIL Lab test result of top dome cube (M-30) found unsatisfactory.(29.89 N/mm2) | |||||||||||||
| 42 | 20021622 | Kudi | 20021622/01 | No | No | No | No | No | No | No | No | No | No | No | No | No | Construction of OHT staircase 5th & 6th landing not as per drawing(Width and Alignment ) issue. Alignment of stair is repaired and verified by Site engineer along with upjn. | |||||||||||||