Agency-wise Major/critical Ncs at OHT

S.No. Scheme ID Scheme Name OHT Code Non-Compliance Compliance(Current Status)
Description
Major Honey Comb Alignment Cube Test Exposure Deviation Tank Observation Other SBC Issue Demolish Partially Demolish Fully Under Examination Serious Observation Water Body Compliance Major Honey Comb Compliance Alignment Compliance Cube Test Compliance Exposure Compliance Deviation Compliance Tank Compliance Other Compliance SBC Issue Compliance Demolish Partially Compliance Demolish Fully Compliance Under Examination Compliance Serious Observation Compliance Water Body
1 20086378 ANDHIPUR GRAM PANCHAYAT WATER SUPPLY SCHEME 20086378/01 No No No Yes No No No No No No No No No Resolved Observation-Reinforcement has been found in expose condition in 2nd brace of OHT. on Dated 24/09/2025 Compliance submitted-Clean and apply Fosroc nitobond EP with normal paint brush. And to wait for 24 hrs, after remove the formed layer of loose with wire brush. * Apply Nitozinc Primer (or equivalent) on reinforcement. * After One hour the surface is to be smooth finished with Fosroc Renderoc SP 40 (or equivalent). * Apply the curing compound as soon as the surface water disappears but before the repair material dries up.
2 20100723 NADESAR GRAM PANCHAYAT WATER SUPPLY SCHEME 20100723/01 No No No Yes No No No No No No No No No Resolved Observation:OHT column reinforcement has been found in exposed . on dated 30/06/2025 Compliance-Compliance submitted-Clean and apply Fosroc nitobond EP with normal paint brush. And to wait for 24 hrs, after remove the formed layer of loose with wire brush. * Apply Nitozinc Primer (or equivalent) on reinforcement. * After One hour the surface is to be smooth finished with Fosroc Renderoc SP 40 (or equivalent). * Apply the curing compound as soon as the surface water disappears but before the repair material dries up.
3 20092821 KHARAUJA GRAM PANCHAYAT WATER SUPPLY SCHEME 20092821/01 No Yes No No No No No No No No No No No Observation-Column of OHT has not been found in alignment. On Dated 11/08/2025
4 20086354 LAKHMAPUR GRAM PANCHAYAT WATER SUPPLY SCHEME 20086354/01 No Yes No No No No No No No No No No No Observation-Column above 1st brace Beam of OHT was not found in proper alignment. On Dated 01/07/2025
5 20088716 SAKRA MAU water supply 20088716/01 No No No Yes No No No No No No No No No Observation-Reinforcement has been found in expose condition in 2nd brace of OHT. On Dated 21/08/2025
6 20086178 KACHHARA GRAM PANCHAYAT WATER SUPPLY SCHEME 20086178/01 No Yes No No No No No No No No No No No Observation-1st brace of OHT has not been found in alignment. On Dated-24/09/2025
7 20095308 SAUDMA GRAM PANCHAYAT WATER SUPPLY SCHEME 20095308/01 No No No No Yes No No No No No No No No Observation-Tread of 3rd flight of OHT staircase was not as per specified in drawing. On Dated 30/06/2025
8 20100725 KHEMIPUR GRAM PANCHAYAT WATER SUPPLY SCHEME 20100725/01 No No No No Yes No No No No No No No No Observation-OHT staircase construction has not been done as per drawing. On Dated 09/06/2025