| 1 |
Jhansi |
8157263 |
BAMHROULI VILLAGE WATER SUPPLY SCHEME |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
304.32 |
89.11 |
89.11 |
0.00 |
215.21 |
304.32 |
Under Construction |
73.00 |
The work of scheme is currently in progress, and a partial daily water supply has already been established in the village. All remaining work—including Laying of around 350 m of 63 mm HDPE, 225 m of 90 mm HDPE pipeline, Interconnection works, approximately 150-200 FHTC, 500 meters of CC road restoration and structural painting and finishing—is scheduled for completion by the end of November 2026. Earlier it was disputed due to variation more than 15%, Now the matter is resolved and expected bil |
| 2 |
Jhansi |
20072943 |
Karguwan Village Water Supply Scheme |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
266.89 |
65.51 |
65.51 |
0.00 |
201.38 |
266.89 |
Under Construction |
84.00 |
The work of scheme is currently in progress, and a partial daily water supply has already been established in the village. All remaining work—including approxi 50 functional household tap connections, 50 to 100 meters of concrete road restoration (In Patches due to repair of leakage in pipeline), and structural painting and finishing—is scheduled for completion by the end of November 2026. Earlier it was disputed due to variation more than 15%, Now the matter is resolved and expected bill upload |
| 3 |
Jhansi |
20093452 |
Ambargarh Retrofitting Water Supply Scheme |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
286.97 |
152.13 |
152.13 |
0.00 |
134.84 |
286.97 |
Under Construction |
84.00 |
work of scheme is in progress, and a partial RWS has already been established in village. All remaining work including approxi 85 functional HH tap connections, 50 to 100 meters of CC road restoration (in patches due to pipeline leakage repairs), 250 meters of interlocking road repairs, and structural painting and finishing—is scheduled for completion by the end of November 2026. Earlier it was disputed due to variation more than 15%, Now the matter is resolved and expected bill uploaded on UP |
| 4 |
Jhansi |
20100879 |
Haibatpura G.O.V. W/S Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
347.79 |
34.19 |
34.19 |
0.00 |
313.60 |
347.79 |
Under Construction |
73.00 |
Funding shortages have severely delayed progress on the schemes, as contractor payments have been outstanding for two years. As a result, the remaining work is moving at a sluggish pace.
The following balance works are currently pending completion:
• Distribution Pipeline: Around 1,500 m
• Feeder Main (150 mm dia): 2,100 m
• Pipeline Interconnections: Pending at 5–6 locations
• Road Restoration: 2,100 m (both Cement Concrete [CC] and interlocking tiles) |
| 5 |
Jhansi |
20101021 |
Prithvipura Naya Khera G.O.V. W/S Scheme. |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
368.35 |
62.00 |
62.00 |
0.00 |
306.35 |
368.35 |
Under Construction |
79.00 |
• Two years of outstanding contractor payments have slowed work to a sluggish pace.
• Pending Pipelines: Main feeder main 8.0 km and village distribution interconnection
• Interconnections & Mechanical: 5 to 6 pipeline interconnections and the booster pump installation/interconnection.
• Connections & Finishing: Around 250 Functional Household Tap Connections (FHTCs) and final structural painting/finishing. |
| 6 |
Jhansi |
20101027 |
Saiyyar Village W/S Reorganization Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
520.21 |
109.24 |
109.24 |
0.00 |
410.97 |
520.21 |
Under Construction |
73.00 |
• Contractor payments are two years overdue, causing work to progress at a very slow pace.
• Pending Pipelines: 3.0 km of main feeder main and 3.0 km of distribution pipeline.
• Interconnections & Pumps: Pipeline interconnections at 5–6 locations, alongside booster pump installation and its interconnection.
• Connections & Civil: 250 Functional Household Tap Connections (FHTCs) and final painting/finishing work of the structures. |
| 7 |
Jhansi |
20101030 |
Simrawari Village W/S Reorganization Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1000.89 |
338.43 |
338.43 |
0.00 |
662.46 |
1000.89 |
Under Construction |
73.00 |
• Payments Delayed: Contractor payments are two years overdue, causing significant delays. Consequently, remaining tasks are being executed at a very slow pace.
• Pipeline Works:
• Main Feeder Main: 700 m remaining.
• Distribution Pipeline: 1.5 km outstanding.
• Interconnections: 5 to 6 locations pending.
• Other Works:
• Booster Pump: Installation and interconnection pending.
• FHTCs: 50 tap connections remaining.
• Finishing: Structure painting and finishing work is incomplete.
|