| 1 |
Jhansi |
8157263 |
BAMHROULI VILLAGE WATER SUPPLY SCHEME |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
304.32 |
89.11 |
89.11 |
0.00 |
215.21 |
304.32 |
Under Construction |
65.00 |
Due to negligence in execution of the works and failure to complete them within the stipulated time by the previously contracted firm, its contract was terminated. Thereafter, a new firm was engaged through tendering for the completion of the remaining works. However, owing to the non-availability of funds, the progress of the works is slow. |
| 2 |
Jhansi |
20072943 |
Karguwan Village Water Supply Scheme |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
266.89 |
65.51 |
65.51 |
0.00 |
201.38 |
266.89 |
Under Construction |
70.00 |
Due to negligence in execution of the works and failure to complete them within the stipulated time by the previously contracted firm, its contract was terminated. Thereafter, a new firm was engaged through tendering for the completion of the remaining works. However, owing to the non-availability of funds, the progress of the works is slow. |
| 3 |
Jhansi |
20076755 |
Basari Village Water Supply Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
185.93 |
54.67 |
54.67 |
0.00 |
131.26 |
185.93 |
Under Construction |
85.00 |
Due to failure of Tube well water supply not started in the village. |
| 4 |
Jhansi |
20093452 |
Ambargarh Retrofitting Water Supply Scheme |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
286.97 |
152.13 |
152.13 |
0.00 |
134.84 |
286.97 |
Under Construction |
70.00 |
Due to negligence in execution of the works and failure to complete them within the stipulated time by the previously contracted firm, its contract was terminated. Thereafter, a new firm was engaged through tendering for the completion of the remaining works. However, owing to the non-availability of funds, the progress of the works is slow. |
| 5 |
Jhansi |
20100879 |
Haibatpura G.O.V. W/S Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
347.79 |
34.19 |
34.19 |
0.00 |
313.60 |
347.79 |
Under Construction |
60.00 |
Distribution network of 2 village and FHTC work still pending |
| 6 |
Jhansi |
20100906 |
Siyawari G.O.V. W/S Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
402.45 |
38.04 |
38.04 |
0.00 |
364.41 |
402.45 |
Under Construction |
80.00 |
This scheme in connected from imlota GOV w/s scheme .Interconnection and distribution network still pending |
| 7 |
Jhansi |
20101021 |
Prithvipura Naya Khera G.O.V. W/S Scheme. |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
368.35 |
62.00 |
62.00 |
0.00 |
306.35 |
368.35 |
Under Construction |
75.00 |
This scheme is connected from burhpura GOV w/s scheme .Main Feeder Distribution network still pending |
| 8 |
Jhansi |
20101027 |
Saiyyar Village W/S Reorganization Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
520.21 |
109.24 |
109.24 |
0.00 |
410.97 |
520.21 |
Under Construction |
70.00 |
This scheme connected from Jhansi augmentation water supply scheme(110 MLD) clear water rising Main and Distribution Network Still pending . |
| 9 |
Jhansi |
20101030 |
Simrawari Village W/S Reorganization Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1000.89 |
338.43 |
338.43 |
0.00 |
662.46 |
1000.89 |
Under Construction |
70.00 |
This scheme connected from Jhansi augmentation water supply scheme(110 MLD) clear water rising Main and Distribution Network Still pending . |