| 1 |
Lalitpur |
20099714 |
JAITUPURA VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
68.30 |
6.56 |
6.56 |
0.00 |
61.74 |
68.30 |
Under Construction |
82.00 |
• The scheme is located in Madawara Block and covers one village under the tubewell-based New Retrofitting category.(left out village)
• The target has been set to complete the scheme by 30 October
• pending bill is 5.42 lakhs.
• The proposed borewell has been completed, and the pump house has been constructed.
• Pump lowering and solar system installation are still pending.
• Against the target of 60 FHTCs, all 60 FHTCs remain pending.
• During the current week, 800 metres of pipeline has |
| 2 |
Lalitpur |
20099746 |
BADWAR VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
89.29 |
19.24 |
19.24 |
0.00 |
70.05 |
89.29 |
Under Construction |
85.00 |
• The scheme is located in Madawara Block and covers one village under the tubewell-based New Retrofitting category.(left out village)
• Out of the total 4.50 km distribution pipeline, 3.00 km has been laid and 1.50 km remains pending.
• Pipeline testing is 100% pending.
• All 192 FHTCs are yet to be completed.
• The pump house civil work has been completed, while motor installation and solar system installation are pending.
• All 3 proposed borewells have been completed, and pipe lowering work |
| 3 |
Lalitpur |
20099749 |
KURRAT VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
135.10 |
18.40 |
18.40 |
0.00 |
116.70 |
135.10 |
Under Construction |
100.00 |
|