| 1 |
Pratapgarh |
8130432 |
Dulhipur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
154.77 |
56.08 |
56.08 |
0.00 |
98.69 |
154.77 |
Under Construction |
80.00 |
Progress of Work is slow (T.well- 100%, Pipe Line- 70%, OHT-70%) |
| 2 |
Pratapgarh |
8130580 |
Amari Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
173.57 |
16.84 |
16.84 |
0.00 |
156.73 |
173.57 |
Under Construction |
79.00 |
Progress of Work is slow (T.well- 100%, Pipe Line- 70%, OHT-65%) |
| 3 |
Pratapgarh |
8130665 |
Teliyani Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
201.13 |
71.76 |
71.76 |
0.00 |
129.37 |
201.13 |
Under Construction |
78.00 |
Progress of Work is slow (T.well- 70%, Pipe Line- 80%, OHT-90%) |
| 4 |
Pratapgarh |
8130687 |
Chaupai Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
172.51 |
54.85 |
54.85 |
0.00 |
117.66 |
172.51 |
Under Construction |
81.00 |
Progress of Work is slow (T.well- 70%, Pipe Line- 80%, OHT-90%) |
| 5 |
Pratapgarh |
8130701 |
Kadipur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
225.17 |
90.62 |
90.62 |
0.00 |
134.55 |
225.17 |
Under Construction |
76.00 |
Progress of Work is slow (T.well- 70%, Pipe Line- 65%, OHT-90%) |
| 6 |
Pratapgarh |
8130712 |
Kishungarh Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
190.27 |
43.77 |
43.77 |
0.00 |
146.50 |
190.27 |
Under Construction |
95.00 |
Work in Progress (T.well- 100%, Pipe Line- 90%, OHT-95%) |
| 7 |
Pratapgarh |
8130879 |
Lachhipur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
186.84 |
48.91 |
48.91 |
0.00 |
137.93 |
186.84 |
Under Construction |
95.00 |
Work in Progress (T.well- 100%, Pipe Line- 90%, OHT-95%) |
| 8 |
Pratapgarh |
8131586 |
PURAB GAON |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
198.66 |
42.41 |
42.41 |
0.00 |
156.25 |
198.66 |
Under Construction |
90.00 |
Work in Progress (T.well- 90%, Pipe Line- 90%, OHT-95%) |