| 1 |
Sultanpur |
8132007 |
LAUHAR DAXIN W/S SCHEME |
JJM (JAL NIGAM SCHEMES) |
Jal Nigam |
YES |
NO |
NO |
452.75 |
166.18 |
166.18 |
0.00 |
286.57 |
452.75 |
Under Construction |
88.00 |
Tubewells: 2 Nos. – Completed.
Pumping Plant: 1 No. – Installation completed. The Servocon engineer visited the site to inspect the servo voltage stabilizer and recommended an electrical inspection. Upon inspection, the electrician reported that the motor is tripping due to a decline in the groundwater level, resulting in insufficient submergence of the pump. Installation of additional column pipes in the tubewell is required to ensure adequate pump submergence and resolve the issue. The matter |