| 1 |
Bahraich |
7624357 |
Kandara PWS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
128.54 |
88.54 |
88.54 |
0.00 |
40.00 |
128.54 |
Under Construction |
70.00 |
"The project remains incomplete because the land is disputed and the High Court has ruled in favour of the farmer. Under the scheme, the tank, boring, works are finished. The Tehsil is now processing the allocation of another plot of land to the farmer in exchange." Late No of This office 1175/W-8/55 Date 03.09.2026 & CDO Sir Ltr No I/1414722/2026 Date 14.09.2026 |
| 2 |
Bahraich |
8130812 |
PATHARKALA |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
181.48 |
72.73 |
72.73 |
0.00 |
108.75 |
181.48 |
Under Construction |
85.00 |
The construction of the scheme's tank is in progress, and concreting of the top dome is currently completed. The target to complete the OHT work is 10th November, and the entire scheme is targeted for completion by 15th November. and the water supply will be started with in 10 days. |