| S.No. | District | Scheme ID | Scheme Name | Program Name | Department | PWS Exist | Physical Completion | Financial Completion | Work Cost | Released Cost | Expenditure Cost | Liability | Balance Fund | Final Cost | Scheme Status | Physical Progress(%) | Remark |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | 8130812 | PATHARKALA | NRDWP | Jal Nigam | YES | NO | NO | 181.48 | 72.73 | 72.73 | 0.00 | 108.75 | 181.48 | Under Construction | 85.00 | The construction of the scheme's tank is in progress, and concreting of the top dome is currently completed. The target to complete the OHT work is 10th November, and the entire scheme is targeted for completion by 15th November. and the water supply will be started with in 10 days. |