Jal Nigam ongoing and retrofit new scheme completion plan

District : Banda

Sno Scheme Id Scheme Name Scheme Completion Remarks Expected Completion Date
1 20098809 Kamasin G.O.V reorganisation scheme In Kamasin Village, the Kamasin GoV Reorganisation Water Supply Scheme physical progress is underway. Twelve gap closings and 30% pipeline commissioning are pending, along with 2.5 km of CC restoration, 1.6 km of BOE restoration, and 1.5 km of pipeline laying work. 30-Nov-2025