| Sno |
Scheme Id |
Scheme Name |
Scheme Completion Remarks |
Expected Completion Date |
| 1 |
8127723 |
TENDUA |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 2 |
8376738 |
Kamai |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 3 |
8127719 |
NIGOHAN |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 4 |
8127704 |
KHAIRAHANA |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 5 |
7568672 |
Brahmani QPV Scheme 2016 17 |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 6 |
8128334 |
Dharupur |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 7 |
8157225 |
Bhuwanshahpur |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 8 |
8127721 |
SIJNI |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 9 |
8157559 |
Bhaganpur |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 10 |
8156707 |
Moonghi |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 11 |
8158650 |
Naukhera |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 12 |
8156848 |
Kansapur |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 13 |
8156783 |
Korarilakashan shah |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 14 |
7624111 |
Bahapur PWS Scheme QPV |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 15 |
8157124 |
Bhojpur |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 16 |
8158692 |
Singhpur |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 17 |
8158715 |
Vishesharganj |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 18 |
8178225 |
Shahgarh |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 19 |
8158664 |
Semra |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 20 |
8157570 |
Ratapur |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 21 |
8156733 |
Nagardeeh |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 22 |
7506727 |
Karnaipur QPV Scheme 2016 17 |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 23 |
7506724 |
Barauliya PWS Scheme |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 24 |
8156668 |
Guara |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 25 |
8128277 |
Kachnaaw |
Physically Completed, Final Bill has been prepared. |
31-Dec-2025 |
| 26 |
7618016 |
Sarai Hridayshah QPV Scheme 2016 17 |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |
| 27 |
7618002 |
Dhanapur QPV Scheme 2016 17 |
Physically Completed, Final Bill Pending. |
31-Dec-2025 |