| 1 |
1735870 |
Kiratpur PWS |
2008-2009 |
PWS |
Completed |
19.92 |
19.92 |
19.92 |
0.00 |
O&M |
|
| 2 |
2754619 |
Chhacha |
2009-2010 |
PWS |
Completed |
244.33 |
206.79 |
206.79 |
0.00 |
O&M |
|
| 3 |
3101812 |
LAHRA MAHUAN VILL W/S UNDER S.C./S.T. PIPE WATER SUPPLY PROGRAMEE |
2009-2010 |
PWS |
Completed |
47.88 |
47.88 |
47.88 |
0.00 |
O&M |
|
| 4 |
6192619 |
PUNDAI VILLAGE WATER SUPPLY SCHEME |
2012-2013 |
PWS |
Completed |
205.85 |
205.85 |
205.85 |
0.00 |
O&M |
|
| 5 |
6192664 |
SAMAN VILLAGE WATER SUPPLY SCHEME |
2012-2013 |
PWS |
Completed |
294.27 |
294.27 |
294.27 |
0.00 |
O&M |
|
| 6 |
6192673 |
SAUJ VILLAGE WATER SUPPLY SCHEME |
2012-2013 |
PWS |
Completed |
229.79 |
227.80 |
227.80 |
0.00 |
O&M |
|
| 7 |
6192688 |
KOSHMA HINOOD VILLAGE WATER SUPPLY SCHEME |
2011-2012 |
PWS |
Completed |
198.85 |
198.85 |
198.85 |
0.00 |
O&M |
|
| 8 |
6804725 |
KANKAN WATER SUPPLY SCHEME |
2007-2008 |
PWS |
Completed |
54.56 |
51.44 |
51.44 |
0.00 |
O&M |
|
| 9 |
6804784 |
KUCHELA WATER SUPPLY SCEHEME |
2013-2014 |
PWS |
Completed |
370.80 |
352.95 |
349.55 |
3.40 |
O&M |
|
| 10 |
6825361 |
Naseerpur village water supply scheme |
2014-2015 |
PWS |
Completed |
120.21 |
120.21 |
120.21 |
0.00 |
O&M |
|
| 11 |
7374389 |
KOSMA NRWSP PWS SCHEME 2015 16 |
2015-2016 |
PWS |
Completed |
359.07 |
353.62 |
353.62 |
0.00 |
O&M |
|
| 12 |
7374392 |
GANGSI NRWSP PWS SCHEME 2015 16 |
2015-2016 |
PWS |
Completed |
414.65 |
414.65 |
414.65 |
0.00 |
O&M |
|
| 13 |
7618351 |
RATHERA VILLAGE WATER SUPPLY SCHEME (UNDER SAGY) |
2016-2017 |
PWS |
Completed |
156.98 |
140.42 |
140.42 |
0.00 |
O&M |
|
| 14 |
7618356 |
SAGAMAI VILLAGE WATER SUPPLY SCHEME(UNDER SAGY) |
2016-2017 |
PWS |
Ongoing |
164.67 |
151.40 |
151.40 |
0.00 |
O&M |
|
| 15 |
7894260 |
Dudgaon SAGY PWS Scheme |
2018-2019 |
PWS |
Completed |
184.66 |
121.82 |
121.82 |
0.00 |
O&M |
|
| 16 |
7894265 |
Bamhori SAGY PWS Scheme |
2018-2019 |
PWS |
Completed |
200.79 |
127.81 |
127.81 |
0.00 |
O&M |
|
| 17 |
8016626 |
NAGLA PANDEY VILLAGE WATER SUPPLY SCHEME |
2019-2020 |
PWS |
Ongoing |
66.88 |
53.99 |
49.28 |
4.71 |
O&M |
|
| 18 |
8024203 |
PIPE LINE EXTENTION FHTC WORK IN KOSMA MUSALMEEN VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
64.70 |
51.81 |
50.31 |
1.50 |
O&M |
|
| 19 |
8024518 |
PIPE LINE EXTENTION FHTC WORK IN LAHRA MAHUAN VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Completed |
32.23 |
29.32 |
28.44 |
0.88 |
O&M |
|
| 20 |
8024562 |
PIPE LINE EXTENTION FHTC WORK IN SAUJ VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
102.18 |
52.49 |
43.71 |
8.78 |
O&M |
|
| 21 |
8024585 |
PIPE LINE EXTENTION FHTC WORK IN JOT VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
88.93 |
76.18 |
76.18 |
0.00 |
O&M |
|
| 22 |
8024601 |
PIPE LINE EXTENTION FHTC WORK IN KIRTHUA VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
66.36 |
42.28 |
35.67 |
6.61 |
O&M |
|
| 23 |
8024615 |
FHTC WORK IN KUCHELA VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
55.49 |
44.46 |
41.54 |
2.92 |
O&M |
|
| 24 |
8024623 |
FHTC WORK IN GANGSI VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
42.75 |
21.26 |
21.26 |
0.00 |
O&M |
upjn) ADD ON UPJN PORTAL & Rs. 2.61419 lacs (token No-61366 upjn) ADD ON IMIS PORTAL |
| 25 |
8024641 |
PIPE LINE EXTENTION FHTC WORK IN NASEERPUR VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Completed |
20.28 |
18.18 |
18.18 |
0.00 |
O&M |
|
| 26 |
8024712 |
PIPE LINE EXTENTION FHTC WORK IN SAMAN VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
301.28 |
261.01 |
261.01 |
0.00 |
O&M |
|
| 27 |
8024723 |
PIPE LINE EXTENTION FHTC WORK IN KANKAN VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
119.95 |
99.07 |
97.16 |
1.92 |
O&M |
|
| 28 |
8024733 |
PIPE LINE EXTENTION FHTC WORK IN KOSMA HINOOD VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
186.02 |
113.08 |
111.62 |
1.46 |
O&M |
|
| 29 |
8024739 |
PIPE LINE EXTENTION FHTC WORK IN PUNDARI VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
182.06 |
161.66 |
150.42 |
11.24 |
O&M |
|
| 30 |
8024752 |
PIPE LINE EXTENTION FHTC WORK IN KARIMGANJ VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
146.74 |
93.74 |
93.74 |
0.00 |
O&M |
|
| 31 |
8125750 |
LALUPUR MURHOLI VILLAGE WATER SUPPLY SCHEME |
2019-2020 |
PWS |
Ongoing |
290.01 |
186.47 |
186.47 |
0.00 |
O&M |
|
| 32 |
8126622 |
PIPE LINE EXTENTION FHTC WORK IN CHACHHA VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
285.35 |
247.86 |
246.13 |
1.72 |
O&M |
|
| 33 |
8126659 |
PIPE LINE EXTENTION FHTC WORK IN PARONKH VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
65.98 |
56.42 |
50.96 |
5.46 |
O&M |
|
| 34 |
8172172 |
PIPE LINE EXTENTION FHTC WORK IN KEERATPUR VILLAGE WATER SUPPLY SCHEME |
2020-2021 |
Retrofit |
Ongoing |
137.11 |
100.69 |
100.69 |
0.00 |
O&M |
|