| S.No. | District | Scheme ID | Scheme Name | Program | Physical Completion | Physical Completion (%) | Financial Completion | Work Cost | Released Cost | Expenditure Cost | Liability | Balance Fund | Final Cost | Scheme Status |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 |
| 1 | Sant Kabeer Nagar | 20094676 | KUSAUNA KALAN GP WSS | NEW RETROFIT | NO | 5.00 | NO | 181.30 | 3.60 | 3.60 | 0.00 | 177.70 | 181.30 | Under Construction |
| 2 | Sant Kabeer Nagar | 20094685 | BARPARWA GP WSS | NEW RETROFIT | NO | 20.00 | NO | 172.50 | 28.00 | 28.00 | 0.00 | 144.50 | 172.50 | Under Construction |
| 3 | Sant Kabeer Nagar | 20094694 | GIRDHARPUR GP WSS | NEW RETROFIT | NO | 17.00 | NO | 228.20 | 16.24 | 16.24 | 0.00 | 211.96 | 228.20 | Under Construction |
| 4 | Sant Kabeer Nagar | 20094795 | BARHYA THATHAR GP WSS | NEW RETROFIT | NO | 62.00 | NO | 451.42 | 97.90 | 97.90 | 0.00 | 353.52 | 451.42 | Under Construction |