Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Deoria | Gayatri Projects LTD | 20000647 | Chak Sarain Badal Das Gram Panchayat Water Supply scheme | 218.49 | 100.98 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Deoria | Deoria | Chak Sarain Badal Das | 459604 | Chak Deoria | 4 | 4 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Deoria | Deoria | Chak Sarain Badal Das | 459605 | Parasia Miskari | 169 | 135 | 80 | Work In Progress | Not Certified | Not Verified |
3 | Deoria | Deoria | Chak Sarain Badal Das | 459606 | Chak Sarain Badal Das | 183 | 183 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 20 | 19 | Yes | 0 | NA | No | 6394.00 | 6073.00 |