| Schemes | Villages | < 50% Physical Progress | 51-75% Physical Progress | > 75% Physical Progress | Physically Completed Scheme | Financially Completed Scheme |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 255 | 934 | 77 | 87 | 91 | 25 | 0 |
| Schemes | Village | RWS Village Status | ||
| Fully Functional | Partially Functional | Non Functional | ||
|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 |
| 5644 | 9886 | 1712 | 6281 | 1893 |
| Schemes | Villages | Physically Completed Scheme | Physically Completed Village | Financially Completed Scheme | Financially Completed Village | Physically Not Completed /WIP Schemes | Physically Not Completed /WIP Villages | Financialy Not Completed /WIP Schemes | financialy Not Completed /WIP Villags |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
|---|---|---|---|---|---|---|---|---|---|
| 3704 | 5546 | 3501 | 4913 | 1357 | 1909 | 94 | 588 | 2238 | 3655 |
| S. No. | District | Total | Major Repairable | Minor Repairable(Partial Functional) | ||||||||||
| Total | Fully Functional | Work Started | Work Completed | Handed Over to GP | Total | Work Started | Work Completed | Handed Over to GP | Total | Work Started | Work Completed | Handed Over to GP | ||
| Grand Total | 7540 | 1763 | 730 | 620 | 316 | 3032 | 421 | 346 | 315 | 2740 | 309 | 274 | 1 | |
| 1 | Agra | 6398 | 1422 | 577 | 576 | 316 | 2480 | 329 | 329 | 315 | 2491 | 248 | 247 | 1 |
| 2 | Firozabad | 741 | 341 | 37 | 0 | 0 | 282 | 25 | 0 | 0 | 118 | 12 | 0 | 0 |
| 3 | Mathura | 95 | 0 | 31 | 21 | 0 | 27 | 8 | 3 | 0 | 68 | 23 | 18 | 0 |
| 4 | Unnao | 306 | 0 | 85 | 23 | 0 | 243 | 59 | 14 | 0 | 63 | 26 | 9 | 0 |
| SNO | Phase | Total Schemes |
Total Villages Certified Village |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS/No Disruption |
OHT | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Total RWS Villages RWS(%) |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | Phase 1 | 63 | 6529 4567 | 5745 88% | 39317591055 | 44 3908 | 5 551 | 14 2078 | 0 0 | 13675 | 11 | 1699 | 1646 |
| 2 | Phase 2/3/5 |
36293 | 72442 13790 | 45268 62% | 20918850415846 | 9254 17277 | 6788 13907 | 20251 41888 | 818015337 | 1286125510 | 74 | 36437 | 19185 |
| 3 | Phase 4 | 14 | 6113 119 | 0 0% | 000 | 0 0 | 0 0 | 14 6113 | 00 | 14/6113 | 0 | 1818 | 174 |
| 4 | JJM total | 36370 | 85084 18476 | 51013 60% | 24849 9263 16901 | 9298 21185 | 6793 14458 | 20279 50079 | 8180 15337 | 12888 32298 | 85 | 39954 | 21005 |
| 5 | Jal Nigam | 5899 | 10820 8899 | 7993 74% | 17129065375 | 5644 9886 | 0 0 | 255 934 | 00 | 255/934 | 377 | 0 | 0 |
| 6 | Total JJM+JAL Nigam | 42269 | 95904 27375 | 59006 62% | 26561 10169 22276 | 14942 31071 | 6793 14458 | 20534 51013 | 8180 15337 | 13143 33232 | 462 | 39954 | 21005 |
| SNO | Type | Total Schemes |
Total Villages Certified Village |
RWS Villages | Work Completed | Work In Progress | Villages in O&M but not RWS/No Disruption |
OHT | Financial Details (Lakh) | ||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Total RWS Villages RWS(%) |
100%
90% to 99% < 90% |
O&M SchemesVillages |
Trial Run SchemesVillages |
SchemesVillages |
Direct Pumping SchemesVillages |
No RWS SchemesVillages |
Required OHT | Completed OHT | Estimated Cost | Expenditure | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
| 1 | SINGLE VILLAGE SCHEME (JJM) | 16426 | 16407 3852 | 10834 66% | 508623043444 | 4529 4528 | 3084 3084 | 8813 8800 | 33823380 | 52335226 | 5 | 16303 | 8956 | 4588657.15 | 2727821.07 |
| 2 | SINGLE VILLAGE SCHEME (Jal Nigam) | 3728 | 3730 3441 | 2980 80% | 5113392130 | 497 497 | 0 0 | 0 0 | 00 | 00 | 10 | 0 | 0 | 202.45 | 112.20 |
| Total | 20154 | 20137 7293 | 13814 69% | 559726435574 | 5026 5025 | 3084 3084 | 8813 8800 | 33823380 | 52335226 | 15 | 16303 | 8956 | 4588859.60 | 2727933.27 | |
| S.No. | Phase | Total Villages | Total RWS Disruption | Theft Disruption | Power / Electrical Disruption | Tullu Pump Disruption | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total | Resolved | Pending | Total | FIR Lodged | Resolved | Pending (Village) | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | |||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 |
| 1 | Phase 1 | 6529 | 2462 | 2252 | 210 | 61 | 7 | 60 | 1 | 1 | 1432 | 1414 | 17 | 11 | 38 | 38 | 0 | 0 |
| 2 | Phase 2,3,5 | 72442 | 3248 | 2718 | 530 | 1767 | 330 | 1600 | 166 | 156 | 228 | 194 | 34 | 34 | 36 | 32 | 3 | 3 |
| 3 | Phase 4 | 6113 | 0 | 0 | 0 | 0 | ||||||||||||
| 4 | Jal Nigam | 10820 | 284 | 80 | 204 | 11 | 7 | 4 | 4 | 49 | 23 | 25 | 26 | 60 | 21 | 39 | 19 | |
| Total | 95904 | 5994 | 5050 | 944 | 1839 | 337 | 1667 | 171 | 161 | 1709 | 1631 | 76 | 71 | 134 | 91 | 42 | 22 | |
| S.No. | Phase | Total Villages | Total RWS Disruption | Road Widening Disruption | Damage Village Internal Works | Local Repairing Disruption | Total | Pending >15 Days |
|||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total | Resolved | Pending | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | Total | Resolved | Pending | Pending >15Days | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 |
| 1 | Phase 1 | 6529 | 2462 | 2252 | 210 | 457 | 297 | 159 | 155 | 378 | 372 | 6 | 4 | 96 | 71 | 24 | 20 | 205 | 189 |
| 2 | Phase 2,3,5 | 72442 | 3248 | 2718 | 530 | 471 | 261 | 197 | 208 | 326 | 294 | 32 | 27 | 420 | 337 | 78 | 82 | 494 | 477 |
| 3 | Phase 4 | 6113 | 0 | 0 | 0 | 0 | 0 | 0 | |||||||||||
| 4 | Jal Nigam | 10820 | 284 | 80 | 204 | 63 | 7 | 54 | 55 | 43 | 10 | 33 | 33 | 58 | 12 | 46 | 46 | 195 | 174 |
| Total | 95904 | 5994 | 5050 | 944 | 991 | 565 | 410 | 418 | 574 | 420 | 148 | 148 | 747 | 676 | 71 | 64 | 894 | 840 | |
| # | District/Village | Issue Type | Reported Date | Remark |
|---|---|---|---|---|
| 1 | Jhansi / Ninaura |
Road Widening
|
10-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and still not repaired it till now. |
| 2 | Jhansi / Arjar |
Road Widening
|
12-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and not repaired it till now. |
| 3 | Kushi Nagar / Pipra Khurd |
Road Widening
|
12-Jan-2024 | Water Supply hampered due to Road Widening.Approx .5 KM Pipe line Damged & 58 Nos FHTC |
| 4 | Jhansi / Rampura |
Road Widening
|
16-Jan-2024 | Pwd has damaged the pipeline from last 1.5 years and not repaired it till now |
| 5 | Sonbhadra / Maitapur |
Road Widening
|
27-Jul-2024 | ROAD WIDENING DAMAGE WATER PIPE LINE WAITING DEPARTMENT PERMISSION |
| 6 | Saharanpur / Jajwa |
Theft
|
24-Jun-2025 | सोलर पैनल एवं तार चोरी होने के कारण सप्लाई बंद थी l |
| 7 | Prayagraj / Tudihar |
Theft
|
10-Nov-2025 | Solar Theft Reported |
| 8 | Bareilly / Sahasia Hasainpur Mustqil |
Theft
|
08-Jan-2026 | Solar wire theft |
| 9 | Jaunpur / Baihari |
Theft
|
08-Jan-2026 | Solar Module Theft |
| 10 | Sant Kabeer Nagar / Netwapur |
Theft
|
08-Jan-2026 | 2 Nos Solar Module theft from site. |
| 11 | Kushi Nagar / Pokhar Bhinda |
Power/Electrical Issue
|
16-Feb-2024 | Regular Water supply in this village hampered due to Electrical Supply not avilable in this Village. |
| 12 | Kushi Nagar / Brindaban |
Power/Electrical Issue
|
20-Feb-2024 | Only Pole Erection done.Transformer not installed and Connection not Done .So Water Supply not in this Village. |
| 13 | Kushi Nagar / Banka Khas |
Power/Electrical Issue
|
02-Mar-2024 | Regular Water Supply hampered due to Electrical Supply not avilable in this Village. |
| 14 | Kushi Nagar / Parsa Ahatmali |
Power/Electrical Issue
|
02-Mar-2024 | Regular Water Supply hampered in this village due to electrical supply not avilable in this village. |
| 15 | Kushi Nagar / Parsadpur |
Power/Electrical Issue
|
02-Mar-2024 | Regular Water Supply in this village hampered due to Electrical Supply not avilable in this village. |
| 16 | Shravasti / Semaritarhar |
Tullu Pump
|
02-Dec-2025 | Pump has been repairing |
| 17 | Meerut / Sarurpur Khurd |
Tullu Pump
|
15-Dec-2025 | Regular water supply has been operational for over 2 years; however, some villagers have installed direct tullu pumps and removed FCVs from FHTCs, causing pressure issues. |
| 18 | Meerut / Kaithwari |
Tullu Pump
|
12-May-2026 | Approximately 210 villagers have taken unauthorized direct FHTC connections by removing FCVs and installing private tullu pumps, causing severe pressure issues in the remaining area. Notices have been issued and police action has been initiated, but villagers are opposing the removal of these illegal connections. Resolution of this issue will require additional time and continuous follow-up. |
| 19 | Meerut / Sarurpur Khurd |
Tullu Pump
|
10-Jul-2026 | The villagers are taking direct supply by removing the flow control valve (FCV), due to which there is a problem of drinking water supply in the village due to lack of proper pressure in the line. |
| 20 | Kanpur Nagar / Jadepur Dhassa |
Local Repairing
|
19-Feb-2024 | Solar Materials Damaged By Unknown Persons |
| 21 | Kanpur Nagar / Maduri |
Local Repairing
|
10-Aug-2024 | Solar Materials Damaged By Unknown Persons |
| 22 | Shravasti / Shivpur Bankata |
Local Repairing
|
21-May-2025 | Solar Damage |
| 23 | Shravasti / Shivajot |
Local Repairing
|
21-May-2025 | Solar Damage |
| 24 | Shravasti / Mohmmadpur Raja |
Local Repairing
|
01-Jun-2025 | Solar Damage |
| 25 | Sant Kabeer Nagar / Mahadewa |
Damage Village Internal Works
|
21-Jun-2025 | 31 Rmt pipeline damaged by Local Villagers |
| 26 | Sant Kabeer Nagar / Bedo Khor |
Damage Village Internal Works
|
23-Jul-2025 | 175 Rmt pipeline damaged by Local GOVT. Body during road construction work. |
| 27 | Sant Kabeer Nagar / CHEAPUR |
Damage Village Internal Works
|
23-Jul-2025 | 175 Rmt pipeline damaged by Local GOVT. Body during road construction work. |
| 28 | Sant Kabeer Nagar / Dahrauli |
Damage Village Internal Works
|
23-Jul-2025 | 175 Rmt pipeline damaged by Local GOVT. Body during road construction work. |
| 29 | Sant Kabeer Nagar / Suraina |
Damage Village Internal Works
|
28-Jul-2025 | 15 Rmt pipeline damaged by Local Villagers |
| SNo. | Phase | Total Villages | Theft | Power Electrical Issue |
Tullu Pump |
Road Widening |
Damage Village Internal Works |
Local Repairing |
Total | Pending More Than 15 Days |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
| 1 | Phase 1 | 6529 | 1 | 17 | 0 | 76 | 15 | 4 | 111 | 95 |
| 2 | Phase 2,3,5 | 72442 | 44 | 1 | 2 | 39 | 29 | 5 | 115 | 110 |
| 3 | Phase 4 | 6113 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | Jal Nigam | 10820 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| 4 | Total | 95904 | 45 | 18 | 2 | 115 | 44 | 9 | 226 | 205 |
| SNo. | Phase | Total Villages | Certification | Jal Arpan | Jal Aklan | 100% Road Restoration Villages |
|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 1 | Phase 1 | 6529 | 4567 | 997 | 3986 | 5732 |
| 2 | Phase 2,3,5 | 72442 | 13790 | 4465 | 14197 | 55454 |
| 3 | Phase 4 | 6113 | 119 | 0 | 129 | 57 |
| 4 | JJM total | 85084 | 18476 | 5462 | 18312 | 61243 |
| SNo. | Total No of Villages | No of Villages Where RPWSS Finalized | No of Villages Where RPWSS in Draft | No of Village RPWSS not Started | Finalized(%) |
|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | 97070 | 94326 | 1119 | 1625 | 97.17% |
| Sr.No. | Components | Total | Phase 1 | Phase 2,3,5 | Phase 4 | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | Target | Achivement | % | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| 1 | ट्यूबवेल | 38932 | 38535 | 98.98 | 550 | 550 | 100.00 | 38382 | 37985 | 98.97 | 0 | 0 | |
| 2 | पंप हाउस | 38932 | 37764 | 97.00 | 550 | 550 | 100.00 | 38382 | 37214 | 96.96 | 0 | 0 | |
| 3 | क्लोरीनीकरण प्रणाली | 38382 | 25427 | 66.25 | 0 | 0 | 38382 | 25427 | 66.25 | 0 | 0 | ||
| 4 | पाइपलाइन बिछाने का कार्य (कि.मी). | 564249 | 520802 | 92.30 | 58117 | 57460 | 98.87 | 450441 | 425900 | 94.55 | 55691 | 37442 | 67.23 |
| 5 | सौर ऊर्जा प्लांट | 32859 | 29028 | 88.34 | 0 | 0 | 32859 | 29028 | 88.34 | 0 | 0 | ||
| 6 | घरेलू नल कनेक्शन(FHTC) | 22334304 | 20261843 | 90.72 | 1685084 | 1670275 | 99.12 | 18890561 | 18248305 | 96.60 | 1758659 | 343263 | 19.52 |
| 7 | जल शुद्धिकरण संयंत्र (W.T.P) | 72 | 62 | 86.11 | 62 | 62 | 100.00 | 0 | 0 | 10 | 0 | 0.00 | |
| 8 | सड़क मरम्मत का कार्य (KM) | 201141 | 195403 | 97.15 | 10079 | 9685 | 96.09 | 181765 | 177101 | 97.43 | 9297 | 8617 | 92.69 |
| 9 | वे गाँव जहाँ 100% सड़क मरम्मत का कार्य पूर्ण हो चुका है। | 85471 | 61243 | 71.65 | 6547 | 5732 | 87.55 | 72795 | 55454 | 76.18 | 6129 | 57 | 0.93 |
| 10 | ओवरहेड टैंक (OHT) | 39954 | 38960/21005 | 97.51/52.57 | 1699 | 1684/1646 | 99.12/96.88 | 36437 | 35520/19185 | 97.48/52.65 | 1818 | 1756/174 | 96.59/9.57 |
| 11 | कमीशनिंग गाँव | 85471 | 52957 | 61.96 | 6547 | 6353 | 97.04 | 72795 | 46604 | 64.02 | 6129 | 0 | 0.00 |
| SNo. | Phase | Total | O&M | ||||
|---|---|---|---|---|---|---|---|
| Scheme | Integrated | Live | Scheme | Integrated | Live | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 63 | 54 | 39 | 44 | 43 | 33 |
| 2 | Phase 2,3,5 | 36296 | 10960 | 5337 | 9254 | 7872 | 4118 |
| 4 | JJM total | 36359 | 11014 | 5376 | 9298 | 7915 | 4151 |
| ## | Jal Nigam | 5899 | 0 | 0 | 0 | 0 | 0 |
| 4 | All total | 42258 | 11014 | 5376 | 9298 | 7915 | 4151 |
| SNo. | Phase | Total Complaint | O&M Complaint | ||||
|---|---|---|---|---|---|---|---|
| Total | Close | Pending | Total | Close | Pending | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| 1 | Phase 1 | 25614 | 21793 | 3821 | 16293 | 14830 | 1463 |
| 2 | Phase 2,3,5 | 80493 | 71030 | 9463 | 27542 | 24878 | 2664 |
| 3 | Phase 4 | 3090 | 2988 | 102 | 0 | 0 | 0 |
| 4 | Jal Nigam | 13777 | 12128 | 1649 | 3037 | 2465 | 572 |
| 4 | JJM total | 122974 | 107939 | 15035 | 46872 | 42173 | 4699 |
| Sno | Description | Total Villages | Completed Villages | Work In Progress Villages | Completed(%) |
| 1 | 2 | 3 | 4 | 5 | 6 |
|---|---|---|---|---|---|
| 1 | Arsenic | 738 | 559 | 179 | 76 |
| 2 | Fluoride | 1460 | 886 | 574 | 61 |
| 3 | JE/AES | 1146 | 750 | 396 | 65 |
| S. No. | Test By | Test Details | ||||||
| Total Test | Village Tested | Safe found | Contaminated found | Remedial Action | Re-Test | Re-Test found Safe | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
|---|---|---|---|---|---|---|---|---|