Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Welspun Kaveri Infraprojects JV | 20008859 | Sharifpur | 338.32 | 193.91 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 31 | 31 | Yes | 0 | NA | No | 12796.00 | 14619.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Jalalpur | Lakhaniaa | 438273 | Lakhaniya | 345 | 345 | 100 | Har Gar Jal | Certified |
| 2 | Ambedkar Nagar | Jalalpur | Sharif Pur | 438391 | Sharif Pur | 113 | 113 | 100 | Har Gar Jal | Not Certified |
| 3 | Ambedkar Nagar | Jalalpur | Sharif Pur | 438392 | Rukundipur | 227 | 227 | 100 | Har Gar Jal | Not Certified |