Scheme Details
DISTRICT
Pilibhit
AGENCY
PNC-SPML-JV
SCHEME ID
20010154
SCHEME NAME
UGANPUR BISALPUR VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
216.55
EXPENDITURE
135.30
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
2876.00
Meter
Length Laid
2876.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Barkhera | Uganpur Bisalpur | 404888 | Uganpur Bisalpur | 253 | 253 | 100% | Har Ghar Jal | Certified |