Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | PNC-SPML-JV | 20010849 | Khandepur Water Supply Scheme | 246.43 | 164.30 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 6594.00 | 6594.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Bisalpur | Khandepur | 405172 | Khandepur | 247 | 247 | 100 | Har Gar Jal | Certified | 
| 2 | Pilibhit | Bisalpur | Khandepur | 405173 | Rampura Rama | 108 | 108 | 100 | Har Gar Jal | Certified | 
| 3 | Pilibhit | Bisalpur | Khandepur | 405174 | Nawadia Baljeet | 55 | 55 | 100 | Har Gar Jal | Certified |