| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Aligarh | ION EXCHANGE | 20011637 | sikanderpur kota | 274.42 | 176.82 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | Yes | 0 | NA | No | 9318.00 | 8800.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Aligarh | Jawan | SIKANDRAPUR KOTA | 394664 | SIKANDRAPUR KOTA | 290 | 238 | 82 | Work In Progress | Not Certified |
| 2 | Aligarh | Jawan | SIKANDRAPUR KOTA | 394665 | BAHADURPUR KOTA | 219 | 59 | 27 | Work In Progress | Not Certified |