Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | JMC - Lakshmi (JV) | 20012372 | BHAWARI WATER SUPPLY SCHEME | 504.71 | 182.49 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Pratapgarh | Singhipur | Nasirpur | 428722 | Nasirpur | 500 | 500 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Pratapgarh | Singhipur | Bhawari | 428763 | Bhawari | 183 | 183 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Pratapgarh | Singhipur | Bhawari | 428764 | Sarawan | 157 | 157 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 0 | 0 | NA | 16 | NA | No | 30271.00 | 29325.00 |