Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ambedkar Nagar | Welspun Kaveri Infraprojects JV | 20013401 | MUKUNDPUR | 293.88 | 240.42 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ambedkar Nagar | Tanda | Bihra | 437494 | Bihra | 205 | 205 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ambedkar Nagar | Tanda | Bihra | 437495 | Jaganpur | 84 | 84 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ambedkar Nagar | Tanda | Mukundpur | 437632 | Mukundpur | 188 | 188 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Ambedkar Nagar | Tanda | Mukundpur | 437633 | Darveshpur | 32 | 32 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 14041.00 | 13827.00 |