Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | PNC-SPML-JV | 20013699 | BHIKAMPUR URF PRANPUR | 192.14 | 115.52 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 13 | 13 | Yes | 0 | NA | No | 6440.00 | 6847.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Barkhera | Bhikampur Urf Pranpur | 404889 | Bhikampur Urf Pranpur | 188 | 188 | 100 | Har Gar Jal | Certified | 
| 2 | Pilibhit | Barkhera | Bhikampur Urf Pranpur | 404890 | Barkhari | 31 | 31 | 100 | Har Gar Jal | Certified | 
| 3 | Pilibhit | Barkhera | Bhikampur Urf Pranpur | 404891 | Barkhara | 87 | 87 | 100 | Har Gar Jal | Certified |