Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Sitapur | NCC Ltd. | 20016410 | FIROZPUR | 255.52 | 138.50 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Sitapur | Machrehta | Firozpur | 409944 | Akilpur | 166 | 166 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Sitapur | Machrehta | Firozpur | 409945 | Firojpur | 77 | 77 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Sitapur | Machrehta | Firozpur | 409946 | Saraiya | 99 | 99 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 18 | 18 | Yes | 0 | NA | No | 9184.00 | 9184.00 |