| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sambhal | SPML Infra | 20016618 | DUPTA KALAN WATER SUPPLY SCHEME | 352.89 | 160.32 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 14289.00 | 14289.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sambhal | Rajpura | Dupta Kalan | 400873 | Dupta Kalan | 250 | 250 | 100 | Har Gar Jal | Not Certified |
| 2 | Sambhal | Rajpura | SISONA DANDA | 400874 | SISAUNA DANDA | 213 | 213 | 100 | Har Gar Jal | Certified |
| 3 | Sambhal | Rajpura | SISONA DANDA | 400875 | BHOPATPUR | 235 | 232 | 99 | Work In Progress | Not Certified |