Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sambhal | SPML Infra | 20017070 | JUNAWAI WATER SUPPLY SCHEME | 299.15 | 54.83 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 25 | NA | No | 15037.00 | 0.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sambhal | Junawai | Junvih | 401039 | Junvih | 665 | 654 | 98 | Work In Progress | Not Certified |
| 2 | Sambhal | Junawai | Junvih | 401040 | Sarai Brahman | 213 | 205 | 96 | Work In Progress | Not Certified |