Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Hathras ION EXCHANGE 20017618 SHEIKHUPUR AJIT WSS 1203.14 411.61 view more

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
7 6 6 6 6 6 1 0 0 0 NA 48 NA No 35253.00 37261.30

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Hathras Sasni Salempur 395423 Salempur 775 773 100 Work In Progress Not Certified
2 Hathras Sasni Chhonk 395424 Chhonk 516 513 99 Work In Progress Not Certified
3 Hathras Sasni Tatarpur 395425 Tataarpur 230 228 99 Work In Progress Not Certified
4 Hathras Sasni SHEIKHUPUR AJIT 395426 SHEIKHUPUR AJIT 378 289 76 Work In Progress Not Certified
5 Hathras Sasni Amokhri 395427 Amokhri 171 169 99 Work In Progress Not Certified
6 Hathras Sasni Amokhri 395428 Dhatroi 155 147 95 Work In Progress Not Certified
7 Hathras Sasni Bahta 395431 Bahta 188 184 98 Work In Progress Not Certified