Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Shahjahanpur | NCC Ltd. | 20018015 | Shikarpur | 244.82 | 109.63 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Shahjahanpur | Jaitipur | Shikarpur | 406555 | Shikarpur | 132 | 132 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Shahjahanpur | Jaitipur | Shikarpur | 406556 | Bhitara | 154 | 154 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Shahjahanpur | Jaitipur | Shikarpur | 406557 | Jagdishpur | 125 | 125 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 15 | 15 | Yes | 0 | NA | No | 6268.00 | 6268.00 |