Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Approve By Agency Status Approve By EE Status Automation Status
1 Hapur LC INFRA 20019284 AYADNAGAR NORTH + AYADNAGAR SOUTH Water Supply Scheme 355.39 197.55 Verified Verified Not Integrated

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Hapur Hapur Ayadnagar(south) 392542 Ayadnagar(south) 1129 1129 100 Har Gar Jal Certified Not Verified
2 Hapur Hapur Ayadnagar(north) 392543 Ayadnagar(north) 622 622 100 Har Gar Jal Certified Not Verified

Scheme Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 1 30 30 Yes 0 NA No 8853.00 8700.00