Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Chandauli | ION EXCHANGE | 20020001 | Thekaha WS | 559.49 | 223.96 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Chandauli | Shahabganj | Thekha | 475287 | Thekha | 186 | 186 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Chandauli | Shahabganj | Thekha | 475288 | Sobantha | 81 | 81 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Chandauli | Shahabganj | Thekha | 475289 | Israulia | 68 | 68 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Chandauli | Shahabganj | Thekha | 475290 | Sheopur Mafi | 84 | 84 | 100 | Har Gar Jal | Certified | Not Verified |
5 | Chandauli | Shahabganj | Baragaon | 475291 | Baragaon | 327 | 327 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 18 | 18 | Yes | 0 | NA | No | 17904.00 | 17900.00 |