Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Gorakhpur | NCC Ltd. | 20020082 | DADOORA Water supply scheme | 381.98 | 361.98 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Gorakhpur | Uruwa | Dadoora | 455774 | Dadoora | 179 | 179 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Gorakhpur | Uruwa | Dadoora | 455775 | Baijantha | 29 | 29 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Gorakhpur | Uruwa | Dadoora | 455776 | Phariniya Khurd | 38 | 38 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Gorakhpur | Uruwa | Dadoora | 455777 | Amowli | 23 | 23 | 100 | Har Gar Jal | Certified | Not Verified |
5 | Gorakhpur | Uruwa | Dadoora | 455778 | Bowrdeh | 75 | 75 | 100 | Har Gar Jal | Certified | Not Verified |
6 | Gorakhpur | Uruwa | Dadoora | 455779 | Nagwa | 39 | 39 | 100 | Har Gar Jal | Certified | Not Verified |
7 | Gorakhpur | Uruwa | Dadoora | 455780 | Mathbiharidas | 5 | 5 | 100 | Har Gar Jal | Certified | Not Verified |
8 | Gorakhpur | Uruwa | Dadoora | 455782 | Teliabhar | 22 | 22 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
8 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 33 | 33 | Yes | 0 | NA | No | 25582.00 | 20773.00 |