Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Gorakhpur | NCC Ltd. | 20020562 | Govindpur Lonia | 405.78 | 270.32 | Verified | Not Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Gorakhpur | Pali | Govindpur Lonia | 454955 | Lonia | 219 | 219 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Gorakhpur | Pali | Govindpur Lonia | 454956 | Odar | 1 | 1 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Gorakhpur | Pali | Govindpur Lonia | 454957 | Kakuwapar | 26 | 26 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Gorakhpur | Pali | Govindpur Lonia | 454958 | Bishunpur | 58 | 58 | 100 | Har Gar Jal | Certified | Not Verified |
5 | Gorakhpur | Pali | Govindpur Lonia | 454959 | Chigauna | 75 | 75 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 31 | 30 | Yes | 0 | NA | No | 23349.00 | 22056.00 |